PROJECT NAME :  Redevelopment of Park and Parking at Beniabagh Park
Project Detail / Brief Description:

Redevelopment of Park and Parking at Beniabagh Park Best utilization of the Beniabagh park in the interest of citizens and visitors of Varanasi by creating quality of urban green space/avenues and providing formal basement parking to reduce congestion on urban street.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:

Main objective of redevelopment of park and parking project at town hall is to -
1-Efficient utilization of land resources and decongest the roads by providing designated off-street parking space/facility to citizens.
2-Enhancing natural beauty and providing a green space for enriching the spiritual, aesthetic and social life.
3-Creation of platform for superior recreation activities and
4-Ensure active citizen engagement and visitors.
5-Providing attractive and usable green spaces to the public with suitable flowering plants/medicinal plants/shrubs/ climbers.
6-Increased access to open space and recreational areas to the citizens of Varanasi that are safe, promote physical activity.
7-Improved green cover of the city for better environmental quality while preserving the local culture and heritage.
8-Providing Park, kids’ activities area, open gym, pergolas and other facility.
9-Provide space for vendors.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rajesh Kumar Trivedi rajesh.trivedi@repl.global 8840994640 Construction Manager, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 20/Mar/2020 Project Planned Completion Date: 31/Dec/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Waterproofing work and reinforcement work in progr 16/10/2020 31/10/2020 17%
WIP 16/10/2020 31/10/2020 30%
Excavation for basement work in progress. 16/10/2020 31/10/2020 55%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Excavation of Parking
Excavation for basement work in progress. 12/05/2020 31/08/2021 - 90%
2 PCC at basement level
WIP 01/07/2020 31/03/2021 - 90%
3 Raft Work
Waterproofing work and reinforcement work in progress. 12/09/2020 31/08/2021 - 90%
4 slab of parking
WIP 01/02/2021 30/09/2021 - 90%
5 Putti and Primer
WIP 01/05/2021 30/09/2021 - 70%
6 flooring and draining
WIP 01/06/2021 30/09/2021 - 50%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
9042 Lac. 0 Lac. 9042 Lac. 6624 Lac. 2418 Lac.