PROJECT NAME :  Redevelopment of Wards of Old Kashi-Kameshwar Mahadev Ward
Project Detail / Brief Description:

Improvise infrastructure such as water supply, sewerage system, artistic painting and efficient lighting of the ward for better environmental quality while preserving the local culture and heritage.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:

1.Retrofitting of the Old Kashi Streets – Chunar Stone flooring,Strengthening of street service infrastructure 2.Replacement of Sewerage Line 3.Replacement of water supply line 4.Provision of Ducks for laying services in future 5.Artisting painting work on property wall 6.Preserving the character of Old streets of Kashi


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rajesh Kumar Trivedi rajesh.trivedi@repl.global 8840994640 Construction Manager, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 27/Feb/2020 Project Planned Completion Date: 31/Mar/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
Sewer line and Water line work in progress. 16/10/2020 31/10/2020 30%
As per site requirement construction material woul 16/10/2020 31/10/2020 70%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Moblisation of Men power and T&P
done 27/05/2020 30/09/2020 - 100%
2 Procurement of DI PIPE and Accessory for 500 mtr
Completed 27/05/2020 26/10/2020 - 100%
3 Procurement of RCC PIPE and Interconnection for 500 mtr
Completed. 27/05/2020 31/10/2020 - 100%
4 Procurement of Construction Material for 500 mtr water connection
Completed. 01/06/2020 30/10/2020 - 100%
5 Laying of Sewer line in 500 mtr
.Completed 01/06/2020 31/10/2020 - 100%
6 Laying of water line in 500 mtr patch
.Completed 01/06/2020 31/10/2020 - 100%
7 Laying of Sewer line and Water line from 501 mtr to 2000 mtr
Sewer line - 1510 and Water line -1084 mtr completed. chowka stone- 24/08/2020 31/01/2021 - 45%
8 Procurement of Construction Material for 501 mtr to 2000 mtr
WIP 01/09/2020 31/10/2020 - 60%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1709 Lac. 0 Lac. 1709 Lac. 1042 Lac. 667 Lac.