Back     

Project Details

PROJECT NAME :  IPDS - Old Kashi Laying of HT and LT Lanes (2*8 Km) Varanasi
Project Detail / Brief Description:

8 Km towards Ganges bank and 2kms in city side - High Tension (HT) and Low Tension (LT) overhead electrical Networks are being converted into underground through HT and LT Cables.
Construction of new 33/11 KVA power sub-station - Kazzakpura (2*10 MVA),Being commissioned and running commercially,
Chowk (2*10 MVA) WIP - expected completion time December 2017


Project Department:

Integrated Power Development Scheme (IPDS)

Associated Yojna Name:

IPDS

Goals, Objectives and Benefits of Project:

1. Reduction of accidents due to overhead electrical wiring.
2. Reduction of electrical theft and reduction in AT&C losses (Aggregate Technical and commercial losses).
3. Energy saving and increase in revenue.
4. Increase into power supply capacity by 120 MVA.
5. Beautification of city due to reduction in tangled wires.
6. Less power fault and quality electricity supply to consumers.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R.D. Singh uecd2vns@gmail.com 9450963543 Superintendent Engineer
Anil Verma seipdspuvvnl2015@gmail.com 9450963850 Chief Engineer

 PROJECT DATES
Project Planned Start Date: 23/Dec/2015 Project Planned Completion Date: 31/Jan/2018

 METRICS
Key Metrics Current Planned
HT and LT underground cabling 0 KM 3977 KM
Increase in Power Capacity 0 MVA 120 MVA
New Sub-station 0 2
Meter Shifting outside premises 0 80000

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 33KV LINE
TaskDescriptionStart Date End DateStatus
3.5 km LAYING OF UNDER GROUND HT & LT CABLE














16/01/2018 31/01/2018 0%
Laying of 33kv under ground cable.
Target: 47.00 km
Status : WIP
10/01/2016 31/01/2018 - 95%
2 Construction of 33/11KV Sub-station (Kazzakpura)
Construction of new sub-station:
Location : Kazzakpura
Status : Completed
10/01/2016 16/09/2017 - 100%
3 Construction of 33/11KV Chowk Sub-Station
Construction of new sub-station:
Location : Chowk
Status :Completed
10/01/2016 31/01/2018 - 100%
4 Installation of new 11/0.4kv Transformer
Installation of new 11/0.4kv Transformer
Target : 49 Nos.
Completed 45
Status : WIP
10/01/2016 31/01/2018 - 95%
5 11KV LINE
Laying of 11KV under ground cable.
Target : 324.72 km
Status : WIP
10/01/2016 31/01/2018 - 95%
6 LT LINE
Laying of underground LT cable
Target : 1310.00 km
Completed 1165 KM
Status : WIP
10/01/2016 31/01/2018 - 90%
7 Capacity increasing and R&M of 33/11KV Sub-Station
Capacity increasing and R&M of 33/11KV Sub-Station
Target: 09No.
Progress: 09No.
10/01/2016 31/01/2018 - 100%
8 Shifting of Meter
Shifting of Meter.
Target: 54,000 Nos.
Achievement : 50,822 Nos.
10/01/2016 07/02/2018 - 95%
9 Dismantling of Poles
Dismantling of pole 01/02/2018 15/02/2018 - 60%
10 Dismantling of Overhead lines
Dismantling of Overhead lines
16/02/2018 28/02/2018 - 95%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
431.96 Lac. 246.11 Lac. 0 Lac. 246.11 Lac. 431.96 Lac.