Back     

Project Details

PROJECT NAME :  Installation Of Surveillance Camera on 720 Location of the City.
Project Detail / Brief Description:

Camera Installation are in progress different location in city.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sunil Kumar mail@varanasismartcity.gov.in
Rajesh Kumar Trivedi rajesh.trivedi@repl.global 8840994640 Construction Manager, PMC-VSCL
Amrendra Tiwari mail@varanasismartcity.gov.in 9771410338 Senior Engineer

 PROJECT DATES
Project Planned Start Date: 15/Jul/2020 Project Planned Completion Date: 30/Jun/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Duct laying
Work in progress 01/08/2020 31/10/2021 - 74%
2 Fiber laying
WIP 01/09/2020 31/10/2021 - 15%
3 Pole foundation casting

WIP
01/03/2021 31/10/2021 - 80%
4 Pole erection
WIP 01/03/2021 31/10/2021 - 55%
5 Earthing
WIP 01/11/2020 31/10/2021 - 60%
6 RSU installation
WIP 01/11/2020 31/10/2021 - 50%
7 Camera Installation
WIP 01/06/2021 31/10/2021 - 20%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
12804 Lac. 0 Lac. 12804 Lac. 4385 Lac. 8419 Lac.



Back