PROJECT NAME :  Student Activity Centre (G+2) in Rajputana Ground, IIT(BHU),
Project Detail / Brief Description:

Student Activity Centre (G+2) including Water supply,Sanitary installation, Internal Electric installations, Fire Fighting, Fire Alarm system, CTV/LAN and development works at IIT (BHU), Varanasi.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

To create accommodation and dining space for students of IIT(BHU), Varanasi.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 15/May/2020 Project Planned Completion Date: 14/Aug/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Execution of work of external painting and roads. 16/03/2021 31/03/2021 80%
Specialized flooring work in Gymnasium, weight lif 16/03/2021 31/03/2021 10%
1. Flooring work in 2nd floor in progress. 2. Fin 01/06/2021 15/06/2021 100%
1. RCC work level-4 40%. 01/03/2021 15/03/2021 100%
1st floor roof slab casting will be complete. 2nd 01/03/2021 15/03/2021 100%
Column casting for FF roof -50% Brick work upto 01/06/2021 15/06/2021 100%
Column casting for GF roof completed. Ground floor 16/10/2020 31/10/2020 100%
Ground floor roof slab 50% will be casted & 80% sl 01/06/2021 15/06/2021 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 First Milestone
A- Activity Completion of Civil Work:
(a) RCC of Foundation upto plinth level
B- Activity completion of E&M work:
(a) Submission of eligibility documents of associate agencies for E&M works as per eligibility condition.
(b) Submission of shop / layout drawings for conduits /equipments of EI, Fire fighting, CCTV etc. as
required for all E&M services.
(c) Submission of make and model for materials/
equipments to be used for all components of E&M services
15/05/2020 14/09/2020 - 100%
2 Second Milestone
A- Activity completion of Civil Work:
(a) RCC slab upto floor level 2
(b) Brick work upto plinth level
(c) Columns for Badminton court upto floor level 2.
(d) Submission of shop drawings for flooring works of all building complete in all respect.
(e) Submission of shop drawings for truss and roof sheeting works of badminton court, etc.
B- Activity completion of E&M work:
(a) Slab conduiting upto floor level 1
(b) Sample switch, socket, fan fitting etc. installed and complete.
15/09/2020 14/11/2020 - 100%
3 Third Milestone
A- Activity completion of Civil Work:
(a) RCC slab upto floor level 3
(b) Brick work upto floor level 2
(c) Columns for Badminton court upto floor level 3.
B- Activity completion of E&M work:
(a) Slab conduiting upto floor level 2
(b) Wall conduiting upto floor level 2
(c) Sample switch, socket,
15/11/2020 14/01/2021 - 100%
4 Fourth Milestone
A- Activity completion of Civil Work:
(a) All RCC work with Over Head tank, Mumty, Lift machine rooms and Under Ground Tank , etc. complete.
(b) All Brick work all complete.
(c) Internal work upto floor level 4
(d) Water proofing of toilets, internal plumbing work, wall filing work upto floor level 4
B- Activity completion of E&M work:
(a) Slab conduiting upto level 4 (b) Wall conduiting, fixing of switch, socket boxes and DBs upto level 4 (c) Making of holes in toilets, rooms, lift lobby, lift
15/01/2021 14/03/2021 - 100%
5 Fifth Milestone
A- Activity completion of Civil Work:
(i) Completion of internal & external painting, false ceiling of all buildings and flooring,
(ii) Completion of external plumbing, sewerage work, drainage and road work.
B- Activity completion of E&M work:
(a) Installation of fan and fittings in all buildings complete.
(c) Completion & testing of fire fighting and fire alarm work in all building including pump room & yard hydrant work and submission for inspection by CFO.
(d) Service connection to outdoor.
15/03/2021 14/05/2021 - 100%
6 Sixth Milestone
TaskDescriptionStart Date End DateStatus
Sixth Milestone Completion of all works in all respect including testing and commissioning. 01/08/2021 31/08/2021 90%
Completion of all works in all respect including testing and Commissioning. 15/05/2021 30/09/2021 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
2782 Lac. 0 Lac. 1778 Lac. 1963 Lac. 819 Lac.