Project Details

PROJECT NAME :  Tourism Development at Manikarnika Ghat
Project Detail / Brief Description:

Column footing work of foundation is in progress.


Project Department:

Uttar Pradesh Project Corporation Limited

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Raj Nath Yadav pm_3@upprojects.org 9454419141
Vinay Kumar Jain pm3@upprojects.org 8114434325

 PROJECT DATES
Project Planned Start Date: 01/Jun/2021 Project Planned Completion Date: 30/Jul/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Site clearing, leveling, boring & layout work
Site clearing, leveling, boring & layout work completed. 10/06/2021 15/07/2021 - 100%
2 Earth work, P.C.C. work in foundation
Earth work, P.C.C. work in foundation completed. 15/07/2021 30/08/2021 - 100%
3 R.C.C. in raft foundation
R.C.C. in raft foundation work completed. 31/08/2021 31/12/2021 - 100%
4 Slab casting work of stilt floor & column in super structure upto slab of Ground floor
Slab casting work of stilt floor & column in super structure upto slab of Ground floor work completed. 01/01/2022 28/02/2022 - 100%
5 Ground floor slab work & column in super structure for First floor
Shuttering work for Ground floor slab is on progress. 01/03/2022 15/06/2022 - 25%
6 First floor (Satsang Hall) slab work & super structure work
Work will start after completiion of 5th milestone. 16/06/2022 30/08/2022 - 0%
7 Ground floor brick work & electrification, senetary and water supply work without fittings
Work will start after completion of 6th milestone. 01/09/2022 30/09/2022 - 0%
8 Plaster & painting work for inner & outer whole surface
Work will start after completion of 5th activity. 01/07/2022 15/10/2022 - 0%
9 Site development work, sanitary, water supply & electrical fitting
Work will start after completion of 7th activity 16/10/2022 30/11/2022 - 1%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
731 Lac. 0 Lac. 447 Lac. 290 Lac. 441 Lac.