PROJECT NAME : Uraban place making under the Lahartara-Chaukaghat Fly over |
Project Detail / Brief Description:
72% work is completed as per the Scope of Work. |
Project Department: Smart City Varanasi |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Sunil Kumar | mail@varanasismartcity.gov.in | ||
Rajesh Kumar Trivedi | rajesh.trivedi@repl.global | 8840994640 | Construction Manager, PMC-VSCL |
Rajesh Kumar Trivedi | rajesh.trivedi@repl.global | 8840994640 | Construction Manager, PMC-VSCL |
Amrendra Tiwari | mail@varanasismartcity.gov.in | 9771410338 | Senior Engineer |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/May/2021 | Project Planned Completion Date: 15/May/2022 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Site Preparation and leveling | site cleaning work completed | 22/09/2021 | 26/03/2022 | - | 100% |
2 | Pillars Painting Work | Pillars painting work is completed | 23/09/2021 | 12/12/2021 | - | 100% |
3 | Art Work on Pillars | Art Work on Pillars have been completed. | 15/10/2021 | 25/12/2022 | - | 100% |
4 | Soil filling | soil filling work have been competed | 22/09/2021 | 16/03/2022 | - | 100% |
5 | Finishing Jointing railing work | railing work are in progress | 19/10/2021 | 30/04/2022 | - | 90% |
6 | Plantation | Plantation work is in progress | 15/12/2021 | 10/05/2022 | - | 70% |
7 | Constriction of Toilet | Work in progress | 15/12/2021 | 10/05/2022 | - | 65% |
8 | Installation of Shops | Work in progress | 15/12/2021 | 10/05/2022 | - | 65% |
9 | surface paving | work in progress | 15/02/2022 | 15/05/2022 | - | 40% |
10 | waiting area benches seating area | work in progress | 14/02/2021 | 10/05/2022 | - | 70% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
1000 Lac. | 0 Lac. | 1000 Lac. | 556 Lac. | 444 Lac. |