PROJECT NAME :  4 laning of Sultanpur - Varanasi Section of NH-56, Package I.
Project Detail / Brief Description:

4 Laning of Sultanpur to Varanasi Section of NH-56 [Package I] from Km. 134.700 [Design Chainage Km. 134km+700m] to Km. 205.5000 [Design Chainage 209km+230m] in the state of Uttar Pradesh under NHDP Phase IV on EPC mode.


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

NHDP-IV

Goals, Objectives and Benefits of Project:

It will provide better connectivity to major cities like Sultanpur, Pratapgarh & Jaunpur with State Capital and improve the economic condition of the region by Saving travel time and would reduced pollution


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
A. K Rai var@nhai.org 9917463438 DGM (T)
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Jan/2016 Project Planned Completion Date: 28/Jun/2019

 METRICS
Key Metrics Current Planned
Total land under Acquisition 274.94 Hect. Length = 74.53 km 65% of land only is physically available as on date Entire land acquisition is planned to be completed by 31st December 2017

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Milestone II
35% of contract value. Work under progress. 13/04/2017 08/02/2018 - 15%
2 Milestone III
70% of contract value 28/06/2016 28/10/2018 - 0%
3 Milestone IV
100% of Contract value 28/06/2016 28/06/2018 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
98600 Lac. 0 Lac. 0 Lac. 16391 Lac. 82209 Lac.