Project Details

PROJECT NAME :  Varanasi Ring Road Phase-2 Package-2
Project Detail / Brief Description:

Likely Date of Completion 26.03.2023


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Feb/2019 Project Planned Completion Date: 31/Mar/2023

15 Days Task
 Task Name Start Date End Date Percentage(%)
Towards completion Milestone-III. The project is l 01/05/2022 15/05/2022 47%
Towards completion Milestone-III. The project is l 16/04/2022 30/04/2022 45%
Towards completion Milestone-III. The project is 16/04/2022 30/04/2022 45%
Towards completion Milestone-III. The project is 16/04/2022 30/04/2022 45%
Towards completion Milestone-III. The project is 01/04/2022 15/04/2022 45%
Towards completion of Milestone-III. 16/10/2020 31/10/2020 40%
Towards completion of Milestone-III 16/10/2020 31/10/2020 36%
Towards completion of Milestone-III 01/10/2020 15/10/2020 36%
Towards completion of Milestone-III 16/10/2020 31/10/2020 36%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Milestone-III
Towards completion of Mile Stone-III 15/02/2019 26/03/2023 - 44%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
157762 Lac. 157762 Lac. 92126 Lac. 92126 Lac. 223398 Lac.