PROJECT NAME :  Development and Beautification of Chakra and Sonbhadra Pond
Project Detail / Brief Description:

Restoration of the waterbodies as integral natural assets, aesthetical improvement to make it feasible as a potential public area for recreational activities without putting a negative impact on the pond.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:

1. Entrance Plaza with Ticketing Provision. 2. Access and Play area for Differently-abled persons. 3. Aerated fountain and water plants to keep water fresh. 4. Open Gym, Kids play area, Sand pits. 5. Sitting area, Pergola, Gazebo in viewing areas. 6. Boating facilities. 7. Boundary Wall with Artistic & Mural Painting. 8. Landscaping - Jogging Path, Vegetation and Tree Plantation. 9. Directional Signage's. 10.Drinking Water, Public Convince, Adequate Garbage bins.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
D.P. Mishra deo.mishra@repl.global 9990065441 Infrastructure Specialist, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 26/Dec/2019 Project Planned Completion Date: 31/Jan/2021

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Cleaning of Ponds
Cleaning of Chakra Pond has been done.
Cleaning of Sonbhadra Pond work in progress.
03/01/2020 31/10/2020 - 90%
2 Dismantling and Removing of encroachment/waste
Chakra pond dismantling of encroachment, removing and shifting of waste Material have done.
09/01/2020 31/10/2020 - 85%
3 Dewatering
Dewatering has been done on Chakra pond 23/02/2020 31/10/2019 - 75%
4 Boundary Wall Construction
Boundary wall work in progress in Chakra. 31/01/2020 30/11/2020 - 70%
5 Toilet Work
Chakra pond
Footing, plinth beam, column, brick, plaster, electrical,and slab work of toilet completed.
plumbing, extra item work in progress.
25/07/2020 20/10/2020 - 85%
6 Gazebo Work
Chakra pond
Excavation of footing in progress
20/09/2020 31/10/2020 - 80%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
397 Lac. 0 Lac. 71 Lac. 326 Lac.