PROJECT NAME :  Shri Kashi Vishwanath Dham
Project Detail / Brief Description:

Progress updated up to 20-01-2021


Project Department:

Shri Kashi Vishwanath Special Area Development Board, Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
SK Prajapati 3ivishnukant@gmail.com

 PROJECT DATES
Project Planned Start Date: 15/Mar/2020 Project Planned Completion Date: 14/Mar/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
50% GF slab 01/03/2021 15/03/2021 3%
42 Pile casting 01/03/2021 15/03/2021 3%
50% Grade slab , 50% Filler wall 01/03/2021 15/03/2021 5%
Stone cladding & Water proofing 01/03/2021 15/03/2021 6%
50% First Floor slab 01/03/2021 15/03/2021 4%
Ground & First floor flooring 01/03/2021 15/03/2021 5%
50% pile cap 01/03/2021 15/03/2021 0%
50% Brickwork and plaster 01/03/2021 15/03/2021 0%
Stone & Flooring work 01/03/2021 15/03/2021 5%
ground floor slab 01/03/2021 15/03/2021 3%
Grade slab 01/03/2021 15/03/2021 4%
Jetty work 01/03/2021 15/03/2021 0%
Filler wall & grade slab 01/03/2021 15/03/2021 4%
FF floor slab and Grade slab 01/03/2021 15/03/2021 5%
15 No piles 01/03/2021 15/03/2021 1%
Sub-structure up to plinth level. 01/03/2021 15/03/2021 2%
Second floor slab & Ground floor Block masonary 01/03/2021 15/03/2021 12%
water proofing and plaster 01/03/2021 15/03/2021 10%
plaster 01/03/2021 15/03/2021 10%
First floor slab 01/03/2021 15/03/2021 5%
Brick Work for Ground Floor & First Floor 16/03/2021 31/03/2021 1%
Completion of first floor slab 01/02/2021 15/02/2021 5%
Completion of stone Work without final coating 01/02/2021 15/02/2021 5%
Completion of remaining pile cap 01/02/2021 15/02/2021 5%
Completion of grade slab 01/02/2021 15/02/2021 1%
Completion of stone Work without final coating for 01/02/2021 15/02/2021 10%
Completion of structural work for lower GF slab 01/02/2021 15/02/2021 5%
Completion of structural work for above plinth 01/02/2021 15/02/2021 3%
Completion of structural work for first floor slab 01/02/2021 15/02/2021 5%
Completion of balance pile cap work 01/02/2021 15/02/2021 3%
Completion of structural work for First floor 01/02/2021 15/02/2021 5%
Completion of structural work for remaing second f 01/02/2021 15/02/2021 5%
Completion of plastering for all floor 01/02/2021 15/02/2021 1%
FIRST FLOOR WORK IN PROGRESS 16/01/2021 31/01/2021 5%
BALENCE PILE CAP FOUNDATION WORK AND GROUND FLOOR 16/01/2021 31/01/2021 5%
ROOF SLAB & SECOND FLOOR CORRIDOR SLAB WORK IN PRO 16/01/2021 31/01/2021 3%
PILLING WORKING IN PROGRESS 16/01/2021 31/01/2021 4%
FIRST FLOOR WORKS IN PROGRESS 16/01/2021 31/01/2021 5%
STONE WORKS IN ZONE-3 & ZONE-2 & GATE-B WORK IN PR 16/01/2021 31/01/2021 6%
GROUND FLOOR SLAB WORKS IN PROGRESS 16/01/2021 31/01/2021 4%
DIAPHRAM WALL WORKS IN PROGRESS 16/01/2021 31/01/2021 8%
GROUND FLOOR SLAB WORK IN PROGRESS 16/01/2021 31/01/2021 5%
BALANCE PILE FOUNDATION & GROUND FLOOR SLAB WORKS 16/01/2021 31/01/2021 4%
PILE CAP FOUNDATION WORK IN PROGRESS 16/01/2021 31/01/2021 4%
BALANCE GROUND FLOOR SLAB 16/01/2021 31/01/2021 3%
MEZZANINE FLOOR SLAB 16/01/2021 31/01/2021 3%
BALANCE GRADE SLAB & BRICK WORK 16/01/2021 31/01/2021 3%
BALANCE PILE CAP & GROUND FLOOR SLAB 16/01/2021 31/01/2021 13%
GROUND FLOOR SLAB 16/01/2021 31/01/2021 8%
Shop-3 Stone Work Flooring Water Proofing D& 01/01/2021 15/01/2021 13%
Shop-1 Pile Cap 50% 01/01/2021 15/01/2021 4%
Vedic Kendra Pile Cap 50% 01/01/2021 15/01/2021 4%
YSK-III Pile Cap 25% 01/01/2021 15/01/2021 5%
Bhogshala g.f Slab 50% 01/01/2021 15/01/2021 5%
YSK-II GF Slab 40% Masonary (65%) 01/01/2021 15/01/2021 4%
YSK-I Pile Cap 50% 01/01/2021 15/01/2021 4%
Godolia gate GF (LOWER SLAB) 40% 01/01/2021 15/01/2021 5%
Utility block pilling 50% 01/01/2021 15/01/2021 5%
Guest house GF Slab 50% 01/01/2021 15/01/2021 4%
Mumuksha bhavan Gread Beam & Slab 20% SF Slab 10 01/01/2021 15/01/2021 8%
Toilet Block Brickwork and Water Proofing 01/01/2021 15/01/2021 3%
Tourist facility center Grade Slab 50% 01/01/2021 15/01/2021 2%
Varanasi Gallery Completion of stuctural work 50% 01/01/2021 15/01/2021 10%
City Museum Pile Cap 30% 01/01/2021 15/01/2021 3%
Mandir Chowk Brickwork and plaster 50% 01/01/2021 15/01/2021 1%
Mandir Parisar Zone -2 & Gate A (Stone work) (25 01/01/2021 15/01/2021 6%
SHOP-1 Pile cap fds work 16/12/2020 31/12/2020 4%
VEDIC KENDRA PILING WORK 16/12/2020 31/12/2020 4%
YSK-3 Pile cap fdswork 60% 16/12/2020 31/12/2020 3%
YSK-2 PILING, PILE CAP , GRADE SLAB 16/12/2020 31/12/2020 7%
Bhogshala G.F SLAB 16/12/2020 31/12/2020 6%
YSK-1 PILING 35% , PILECAP 50% 16/12/2020 31/12/2020 8%
Godolia Gate G.F slab 70% 16/12/2020 31/12/2020 4%
Guest House Pile cap fdswork 16/12/2020 31/12/2020 5%
Mumuksha Bhavan Pile cap fdswork, grade slab, G. 16/12/2020 31/12/2020 6%
Toilet block Pile cap fdswork, grade slab, structu 16/12/2020 31/12/2020 5%
Tourist Facility Center G.F structural work 16/12/2020 31/12/2020 6%
Varanasi Gallery structural work 16/12/2020 31/12/2020 7%
City Museum pile cap foundation work 16/12/2020 31/12/2020 4%
Mandir Chowk First floor slab 20% , Second floor 16/12/2020 31/12/2020 7%
Mandir Parisar - Zone-I & Gate-C 16/12/2020 31/12/2020 5%
YSK-3 PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 3%
GODOWALIA GATE GROUND FLOOR WORKS 01/12/2020 15/12/2020 5%
MANDIR PARISAR ZONE-1 PILLAR , ARCH , CELLING WO 01/12/2020 15/12/2020 4%
YSK-1 BALENCE PILING WORK & PILE CAP FOUNDAT 01/12/2020 15/12/2020 4%
SHOP-1 PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 4%
VEDIC KENDRA PILLING WORKS 01/12/2020 15/12/2020 5%
VARANASI GALLERY LOWER SLAB WORKS 01/12/2020 15/12/2020 6%
YSK-2 BALANCE PILING WORK & BAL PILE CAP FOUNDAT 01/12/2020 15/12/2020 5%
BHOGSHALA GROUND FLOOR SLAB WORKS (SLAB OVER SHOP 01/12/2020 15/12/2020 5%
GUEST HOUSE PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 5%
TOILET BLOCK BALANCE PILE CAP WORKS 01/12/2020 15/12/2020 5%
MUMUKSHU BHAVAN GRADE SLAB WORKS BALANCE PIL 01/12/2020 15/12/2020 6%
TOURIST FACLITY CENTER SLAB OVER GROOUND FLOOR 01/12/2020 15/12/2020 5%
plastering work 16/11/2020 30/11/2020 1%
piling and pile cap work 16/11/2020 30/11/2020 4%
pile cap work 16/11/2020 30/11/2020 2%
piling work 16/11/2020 30/11/2020 5%
G.F slab work 16/11/2020 30/11/2020 6%
balance pile and pile cap work 16/11/2020 30/11/2020 3%
pile cap work 50% 16/11/2020 30/11/2020 2%
piling work 16/11/2020 30/11/2020 1%
foundation work and G.F slab 16/11/2020 30/11/2020 5%
pilling work 16/11/2020 30/11/2020 4%
balance pile 16/11/2020 30/11/2020 1%
Slab F.F 16/11/2020 30/11/2020 3%
Completion of structural work for above plinth for 16/11/2020 30/11/2020 6%
grade slab 16/11/2020 30/11/2020 3%
structural work for above plinth 16/11/2020 30/11/2020 7%
Completion of stone Work without final coating Zo 16/11/2020 30/11/2020 5%
DREDGING 01/11/2020 15/11/2020 1%
NO WORK 01/11/2020 15/11/2020 0%
excavation & Pile cap fdswork 01/11/2020 15/11/2020 2%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
structural work for G.F 01/11/2020 15/11/2020 6%
NO WORK 01/11/2020 15/11/2020 0%
PLASTERING & STONE WORK 01/11/2020 15/11/2020 4%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
structural work for above plinth upto G.F AND S.F 01/11/2020 15/11/2020 3%
no work 01/11/2020 15/11/2020 0%
Piling work 01/11/2020 15/11/2020 4%
Piling work, excavation & Pile cap fdswork 01/11/2020 15/11/2020 6%
structural work for above plinth for G.F 01/11/2020 15/11/2020 6%
stone Work without final coating on zone 1 & 2. 01/11/2020 15/11/2020 9%
Completion of Piling work 01/11/2020 15/11/2020 4%
PILING WORK, excavation & Pile cap fdswork and st 01/11/2020 15/11/2020 5%
STRUCTURAL WORK 01/11/2020 15/11/2020 6%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
YSK-II 2FS slab, Grade slab & Ground Floor Brickwo 01/11/2020 15/11/2020 5%
Mumuksha Bhavan1st Floor Columns 01/11/2020 15/11/2020 3%
De-shuttering of slab 01/11/2020 15/11/2020 0%
No work 01/11/2020 15/11/2020 0%
YSK-III Pile cap & Excavation in progress 01/11/2020 15/11/2020 5%
Bhogshala-Pile cap work in progress 16/10/2020 31/10/2020 5%
Shop-3 Grade Slab & Masonary work in progress 16/10/2020 31/10/2020 12%
Spiritual book store- Slab casting 16/10/2020 31/10/2020 10%
Mandir Chowk- Ground floor Slab & 2nd Floor Slab i 16/10/2020 31/10/2020 5%
TFC- Pile cap work 16/10/2020 31/10/2020 5%
Godowlia Gate- Pile cap work 16/10/2020 31/10/2020 3%
Varanasi Gallery- backfiiling and tie beam casting 16/10/2020 31/10/2020 2%
YSK-II 2nd Floor slab casting 16/10/2020 31/10/2020 6%
Mumukshu bhavan-Slab casting 16/10/2020 31/10/2020 5%
Toilet Block-Slab casting 16/10/2020 31/10/2020 10%
YSK-I Piling cap work in progress 16/10/2020 31/10/2020 3%
Mandir Parisar-Stone carving pillar & arches fixin 16/10/2020 31/10/2020 10%
YSK-II 1 floor slab work in progress. 01/10/2020 15/10/2020 7%
YSK-I pile work in progress 01/10/2020 15/10/2020 5%
Godolia gate pile work in progress 01/10/2020 15/10/2020 5%
Pile work in progress 01/10/2020 15/10/2020 0%
Mumuksha bhavan slab work in progress 01/10/2020 15/10/2020 10%
Toilet block slab work in progress 01/10/2020 15/10/2020 10%
Pile work in progress 01/10/2020 15/10/2020 5%
Varanasi Gallery column work in progress 01/10/2020 15/10/2020 5%
Mandir chowk- Pile work, 1FS in progress 01/10/2020 15/10/2020 5%
Shop-3 brickwork in progress 01/10/2020 15/10/2020 2%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Yatri Suvidha Kendra I
Yatri Suvidha Kendra I
05/08/2020 30/05/2021 - 17%
2 Shop I
1. External & internal plastering in progress.
05/08/2020 20/04/2021 - 26%
3 Toilet Block
Toilet Block: Total Built-up Area = 204 SQM.
Terrace waterproofing in progress
01/07/2020 06/03/2021 - 45%
4 Mumukshu Bhavan
Mumukshu Bhavan: Total Built-up Area = 1161 SQM.
Sloping slab in progress.
12/07/2020 19/05/2021 - 40%
5 Yatri Suvidha Kendra II
Yatri Suvidha Kendra II: Total Built-up Area = 2859 SQM.
Filler wall in progress.
20/03/2020 27/05/2021 - 36%
6 Shop II
Shop II: Total Built-up Area = 216SQM. 15/08/2020 07/05/2021 - 11%
7 Jetty And Ghat Finishing
Jetty And Ghat Finishing. 19/12/2020 10/06/2021 - 2%
8 Guest House (Tourist)
Guest House (Tourist): Total Built-up Area = 2092.81 SQM.
First floor slab in progress
29/06/2020 24/07/2021 - 20%
9 Varanasi Gallery
Varanasi Gallery: Total Built-up Area = 233 SQM.
23/07/2020 25/05/2021 - 18%
10 General & Ghat Development Works
General & Ghat Development Works: Total Area = 30413 SQM. 03/11/2020 10/08/2021 - 1%
11 Godowlia Gate
Godowlia Gate: Total Built-up Area = 420 SQM.
Grade slab in progress
19/09/2020 27/06/2021 - 16%
12 Vedic Kendra
Vedic Kendra 22/07/2020 28/06/2021 - 8%
13 Mandir Parisar
Mandir Parisar: Total Built-up Area = 1152 SQM. 25/02/2020 27/07/2021 - 12%
14 Tourist Facility Center
Tourist Facility Center
Sloping slab in progress.
10/04/2020 15/06/2021 - 35%
15 Cultural Center
Cultural Center 01/05/2020 30/06/2021 - 9%
16 Utility Block
Utility Block 18/04/2020 15/07/2021 - 1%
17 Security Office
Security Office 23/04/2020 02/07/2021 - 6%
18 Mandir Chowk
Mandir Chowk: Total Built-up Area = 7941.92



16/02/2020 19/05/2021 - 45%
19 Jalpan Kendra
Jalpan Kendra 10/03/2020 01/08/2021 - 9%
20 Spiritual Book Store
Spiritual Book Store 05/03/2020 15/07/2021 - 14%
21 City Museum
City Museum 30/03/2020 29/06/2021 - 18%
22 Shop III
Shop III 30/03/2020 30/01/2021 - 60%
23 Goenka Library
Goenka Library 01/03/2021 11/05/2021 - 1%
24 Bhogshala, Sewadal & Pujari Office
Bhogshala, Sewadal & Pujari Office 25/03/2020 05/05/2021 - 31%
25 Multi Purpose Hall
Multi Purpose Hall 15/04/2020 29/04/2021 - 3%
26 Yatri Suvidha Kendra III
Yatri Suvidha Kendra III 30/03/2020 24/06/2021 - 10%
27 Nilkanth Pavilion
Nilkanth Pavilion 26/04/2020 25/05/2021 - 5%
28 Mandir Parisar
Completion of stone Work without final coating
Zone-I & Gate-C
Zone-II & Gate-A
15/11/2020 30/11/2020 - 15%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
33900 Lac. 0 Lac. 3366 Lac. 3798 Lac. 30102 Lac.