Project Details

PROJECT NAME :  Shri Kashi Vishwanath Dham
Project Detail / Brief Description:

Progress updated up to 30-11-2020


Project Department:

Shri Kashi Vishwanath Special Area Development Board, Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
SK Prajapati 3ivishnukant@gmail.com

 PROJECT DATES
Project Planned Start Date: 15/Mar/2020 Project Planned Completion Date: 14/Mar/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
YSK-3 PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 3%
GODOWALIA GATE GROUND FLOOR WORKS 01/12/2020 15/12/2020 5%
MANDIR PARISAR ZONE-1 PILLAR , ARCH , CELLING WO 01/12/2020 15/12/2020 4%
YSK-1 BALENCE PILING WORK & PILE CAP FOUNDAT 01/12/2020 15/12/2020 4%
SHOP-1 PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 4%
VEDIC KENDRA PILLING WORKS 01/12/2020 15/12/2020 5%
VARANASI GALLERY LOWER SLAB WORKS 01/12/2020 15/12/2020 6%
YSK-2 BALANCE PILING WORK & BAL PILE CAP FOUNDAT 01/12/2020 15/12/2020 5%
BHOGSHALA GROUND FLOOR SLAB WORKS (SLAB OVER SHOP 01/12/2020 15/12/2020 5%
GUEST HOUSE PILE CAP FOUNDATION WORKS 01/12/2020 15/12/2020 5%
TOILET BLOCK BALANCE PILE CAP WORKS 01/12/2020 15/12/2020 5%
MUMUKSHU BHAVAN GRADE SLAB WORKS BALANCE PIL 01/12/2020 15/12/2020 6%
TOURIST FACLITY CENTER SLAB OVER GROOUND FLOOR 01/12/2020 15/12/2020 5%
plastering work 16/11/2020 30/11/2020 1%
piling and pile cap work 16/11/2020 30/11/2020 4%
pile cap work 16/11/2020 30/11/2020 2%
piling work 16/11/2020 30/11/2020 5%
G.F slab work 16/11/2020 30/11/2020 6%
balance pile and pile cap work 16/11/2020 30/11/2020 3%
pile cap work 50% 16/11/2020 30/11/2020 2%
piling work 16/11/2020 30/11/2020 1%
foundation work and G.F slab 16/11/2020 30/11/2020 5%
pilling work 16/11/2020 30/11/2020 4%
balance pile 16/11/2020 30/11/2020 1%
Slab F.F 16/11/2020 30/11/2020 3%
Completion of structural work for above plinth for 16/11/2020 30/11/2020 6%
grade slab 16/11/2020 30/11/2020 3%
structural work for above plinth 16/11/2020 30/11/2020 7%
Completion of stone Work without final coating Zo 16/11/2020 30/11/2020 5%
DREDGING 01/11/2020 15/11/2020 1%
NO WORK 01/11/2020 15/11/2020 0%
excavation & Pile cap fdswork 01/11/2020 15/11/2020 2%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
structural work for G.F 01/11/2020 15/11/2020 6%
NO WORK 01/11/2020 15/11/2020 0%
PLASTERING & STONE WORK 01/11/2020 15/11/2020 4%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
structural work for above plinth upto G.F AND S.F 01/11/2020 15/11/2020 3%
no work 01/11/2020 15/11/2020 0%
Piling work 01/11/2020 15/11/2020 4%
Piling work, excavation & Pile cap fdswork 01/11/2020 15/11/2020 6%
structural work for above plinth for G.F 01/11/2020 15/11/2020 6%
stone Work without final coating on zone 1 & 2. 01/11/2020 15/11/2020 9%
Completion of Piling work 01/11/2020 15/11/2020 4%
PILING WORK, excavation & Pile cap fdswork and st 01/11/2020 15/11/2020 5%
STRUCTURAL WORK 01/11/2020 15/11/2020 6%
NO WORK 01/11/2020 15/11/2020 0%
NO WORK 01/11/2020 15/11/2020 0%
YSK-II 2FS slab, Grade slab & Ground Floor Brickwo 01/11/2020 15/11/2020 5%
Mumuksha Bhavan1st Floor Columns 01/11/2020 15/11/2020 3%
De-shuttering of slab 01/11/2020 15/11/2020 0%
No work 01/11/2020 15/11/2020 0%
YSK-III Pile cap & Excavation in progress 01/11/2020 15/11/2020 5%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Yatri Suvidha Kendra I
Yatri Suvidha Kendra I
05/08/2020 30/05/2021 - 10%
2 Shop I
Shop I : Total Built-up Area = 185 SQM.
PILE CAP work in progress.
05/08/2020 20/04/2021 - 9%
3 Toilet Block
Toilet Block: Total Built-up Area = 204 SQM.
01/07/2020 06/03/2021 - 34%
4 Mumukshu Bhavan
Mumukshu Bhavan: Total Built-up Area = 1161 SQM.
12/07/2020 19/05/2021 - 29%
5 Yatri Suvidha Kendra II
Yatri Suvidha Kendra II: Total Built-up Area = 2859 SQM.
20/03/2020 27/05/2021 - 26%
6 Shop II
Shop II: Total Built-up Area = 216SQM. 15/08/2020 07/05/2021 - 0%
7 Jetty And Ghat Finishing
Jetty And Ghat Finishing. 19/12/2020 10/06/2021 - 0%
8 Guest House (Tourist)
Guest House (Tourist): Total Built-up Area = 2092.81 SQM.
Piling work - 100% Completed.
29/06/2020 24/07/2021 - 10%
9 Varanasi Gallery
Varanasi Gallery: Total Built-up Area = 233 SQM.
23/07/2020 25/05/2021 - 18%
10 General & Ghat Development Works
General & Ghat Development Works: Total Area = 30413 SQM. 03/11/2020 10/08/2021 - 0%
11 Godowlia Gate
Godowlia Gate: Total Built-up Area = 420 SQM. 19/09/2020 27/06/2021 - 13%
12 Vedic Kendra
Vedic Kendra 22/07/2020 28/06/2021 - 1%
13 Mandir Parisar
Mandir Parisar: Total Built-up Area = 1152 SQM. 25/02/2020 27/07/2021 - 8%
14 Tourist Facility Center
Tourist Facility Center 10/04/2020 15/06/2021 - 18%
15 Cultural Center
Cultural Center 01/05/2020 30/06/2021 - 9%
16 Utility Block
Utility Block 18/04/2020 15/07/2021 - 1%
17 Security Office
Security Office 23/04/2020 02/07/2021 - 6%
18 Mandir Chowk
Mandir Chowk: Total Built-up Area = 7941.92



16/02/2020 19/05/2021 - 36%
19 Jalpan Kendra
Jalpan Kendra 10/03/2020 01/08/2021 - 9%
20 Spiritual Book Store
Spiritual Book Store 05/03/2020 15/07/2021 - 14%
21 City Museum
City Museum 30/03/2020 29/06/2021 - 9%
22 Shop III
Shop III 30/03/2020 30/01/2021 - 47%
23 Goenka Library
Goenka Library 01/03/2021 11/05/2021 - 1%
24 Bhogshala, Sewadal & Pujari Office
Bhogshala, Sewadal & Pujari Office 25/03/2020 05/05/2021 - 18%
25 Multi Purpose Hall
Multi Purpose Hall 15/04/2020 29/04/2021 - 1%
26 Yatri Suvidha Kendra III
Yatri Suvidha Kendra III 30/03/2020 24/06/2021 - 9%
27 Nilkanth Pavilion
Nilkanth Pavilion 26/04/2020 25/05/2021 - 5%
28 Mandir Parisar
Completion of stone Work without final coating
Zone-I & Gate-C
Zone-II & Gate-A
15/11/2020 30/11/2020 - 7%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
33900 Lac. 0 Lac. 3366 Lac. 3798 Lac. 30102 Lac.