PROJECT NAME :  Super Specialty Hospital at IMS, BHU, Varanasi
Project Detail / Brief Description:

Construction of Super Specialty Hospital at IMS, BHU, Varanasi


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Ashok Kumar Gupta cpmbhuzone@gmail.com

 PROJECT DATES
Project Planned Start Date: 01/Dec/2017 Project Planned Completion Date: 31/Mar/2019

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Completion of raft foundation works, RCC works in foundation & other works up to plinth level
Completion of raft foundation works, RCC
works in foundation & other works up to
plinth level
And
Making available/bringing two floors of
shuttering (plates, props, beam shuttering
and other accessories (floor area of each
floor - approx. 4500sqm).
01/12/2017 15/02/2018 - 100%
2 Completion of RCC work upto 3rd floor slab
Completion of RCC work upto 3rd floor
slab, brick work upto 1st floor level &
completion of connected E&M conduit
work.
16/02/2018 30/04/2018 - 100%
3 Completion of RCC work upto 7th floor slab & brick work upto 5th floor level
Completion of RCC work upto 7th floor
slab, brick work upto 5th floor level &
completion of connected E&M conduit
work including service building and substation.
01/05/2018 31/07/2018 - 60%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
13544.2 Lac. 0 Lac. 0 Lac. 0 Lac. 13544.2 Lac.