Project Details

PROJECT NAME :  Community Health Center Sarnath Varanasi
Project Detail / Brief Description:


Project Department:

U.P. State Construction & Infrastructure Development Corporation Ltd.

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
manoj kumar srivastav varanasi.upsknn@rediffmail.com 9454456008

 PROJECT DATES
Project Planned Start Date: 24/Jun/2020 Project Planned Completion Date: 31/Oct/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
First Floor RLD 16/03/2021 31/03/2021 80%
Ground Floor 16/03/2021 31/03/2021 100%
RCC work in Foundation 16/03/2021 31/03/2021 100%
Excavation in foundation 01/01/2021 15/01/2021 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Excavation in Foundation
Excavation in Foundation 100% Completed up to Dated 30.11.2020 01/08/2020 31/10/2022 - 100%
2 RCC Work in Foundation
RCC Work in Foundation 07/08/2020 31/10/2022 - 100%
3 Ground Floor
Ground Floor Slab complete, Chinaai complete, Internal plaster work complete, Outer side wall stone work 100% complete, internal wall tiles work 100% complete, sanitary & Water Supply work 40% complete, Boundrywall 50 Mtr Complete 01/11/2020 31/10/2022 - 80%
4 First Floor
First Floor Slab complete, Chinaai complete, Internal plaster work complete, Outer side wall stone work 100% complete, internal wall tiles work 100% complete, sanitary & Water Supply work 40% complete
01/11/2021 31/10/2022 - 80%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
681 Lac. 331 Lac. 303 Lac. 0 Lac. 378 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...