L O A D I N G
Back     

Project Details

PROJECT NAME :  Construction Work of District Drugware House in Varanasi
Project Detail / Brief Description:

मुख्य भवन


Project Department:

Uttar Pradesh Rajkiya Nirman Nigam Limited (UPRNNL) Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. B. Singh gmald.bhadohi@gmail.com 8400400488 Project Manager
UPRNN Varanasi Zone gmvns.bhadohi@gmail.com 9919418282

 PROJECT DATES
Project Planned Start Date: 01/May/2021 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 G
भवन के सुपर स्ट्रक्चर में
चिनाई का कार्य प्रगति पर।
01/05/2022 31/12/2022 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
919 Lac. 192 Lac. 195.01 Lac. 0 Lac. 723.99 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...