PROJECT NAME :  Construction Work of Residential Building in 50 Bedded Women Hospital in Pandeypur, Pandit Deendayal Upadhyay Government Hospital, District Varanasi
Project Detail / Brief Description:

WORK IN PROGRESS


Project Department:

Uttar Pradesh Rajkiya Nirman Nigam Limited (UPRNNL) Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. B. Singh gmald.bhadohi@gmail.com 8400400488 Project Manager
UPRNN Varanasi Zone gmvns.bhadohi@gmail.com 9919418282

 PROJECT DATES
Project Planned Start Date: 01/Feb/2021 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
WORK IN PROGRESS 01/05/2022 15/05/2022 65%
WORK IN PROGRESS 01/05/2022 15/05/2022 35%
WORK IN PROGRESS 01/05/2022 15/05/2022 65%
WORK IN PROGRESS 01/05/2022 15/05/2022 85%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 SENIOR M.O. RES. 01 NOS
WORK IN PROGRESS 15/01/2021 30/06/2022 - 80%
2 M.O. RES. 06 NOS
WORK IN PROGRESS 15/01/2021 30/09/2022 - 35%
3 Type -I, 10 Nos. Residence Building (G+2)
WORK IN PROGRESS 11/11/2021 30/09/2022 - 62%
4 Type -I, 10 Nos. Residence Building (G+2)
WORK IN PROGRESS 11/11/2021 30/09/2022 - 56%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
572.43 Lac. 427.43 Lac. 345 Lac. 0 Lac. 227.43 Lac.