PROJECT NAME :  Construction of 32 room hostel/barrack & 1 scrutiny room in Thana Baragaon
Project Detail / Brief Description:

कार्य पूर्ण।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Jan/2020 Project Planned Completion Date: 30/Apr/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
doors and window fitting 16/04/2022 30/04/2022 40%
painting and flooring work 16/04/2022 30/04/2022 50%
Water proofing work in toilet slabs is in progress 16/04/2022 30/04/2022 65%
Brick work is about to complete 16/03/2022 31/03/2022 100%
Plaster is in progress 16/04/2022 30/04/2022 100%
Scaffolding for Plastering work has been installed 16/04/2022 30/04/2022 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 PAINTING AND FLOORING WORKS
PAINTING AND FLOORING WORKS will be completed within scheduled time 05/04/2022 15/07/2022 - 70%
2 PLUMBING AND INTERNAL ELECTRIFICATION WORKS
PLUMBING AND SANITARY WORKS IS IN PROGRESS 01/03/2022 25/07/2022 - 60%
3 EXTERNAL SITE DEVELOPEMENT
EXTERNAL DEVELOPEMENT AND APPROACH ROAD WILL BE COMPLETED AS PER SCHEDULE 25/04/2022 31/07/2022 - 40%
4 DOORS AND WINDOW FITINGS
DOORS AND WINDOW FITINGS COMPLETED AS PER SCHEDULE 10/04/2022 20/07/2022 - 60%
5 EXTERNAL SEVERAGE WORKS
EXTERNAL SEVERAGE WORKS WILL BE COMPLETED AS PER SCHEDULE 30/04/2022 31/07/2022 - 35%
6 ELECTRIFICATION & FIRE FIGHTING WORKS
ELECTRIFICATION & FIRE FIGHTING WORKS WILL BE COMPLETED AS PER SCHEDULE 01/06/2022 31/07/2022 - 25%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
116 Lac. 116 Lac. 101.36 Lac. 0 Lac. 14.64 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...