PROJECT NAME :  Construction of 40 room hostel/barrack & 1 scrutiny room in Thana Phoolpur
Project Detail / Brief Description:

विवेचना एवं बैरक दोनो के स्ट्रक्चर दीवार कॉलम फ्लोरिंग का कार्य पूर्ण तथा फीनिशिंग का कार्य दिनांक-15-07-2022 तक पूर्ण करा लिया जायेगा।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Jan/2020 Project Planned Completion Date: 30/Mar/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
EXTERNAL SEVERAGE WORK is in progress 16/04/2022 30/04/2022 90%
Work of internal water supply pipes is in progress 16/04/2022 30/04/2022 100%
DOORS AND WINDOW FITINGS works will be completed w 16/04/2022 30/04/2022 100%
Flooring work in barrak has been completed and In 16/03/2022 31/03/2022 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 EXTERNAL SEVERAGE WORKS
EXTERNAL SEVERAGE WORKS will be completed as per schedule 15/03/2022 15/07/2022 - 90%
2 EXTERNAL SITE DEVELOPEMENT
EXTERNAL SITE DEVELOPEMENT will be completed as per schedule 10/04/2022 15/07/2022 - 20%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
133.15 Lac. 133.15 Lac. 133 Lac. 0 Lac. 0.15 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...