SCHEDULE |
Sr. |
Milestone |
Description |
Start Date |
Planned Completion Date |
Actual Completion Date |
Milestone Completion(In %) |
1 | 3rd floor RCC Frame Structure
| Slab casting will be completed by 31st March | 07/11/2020 | 31/03/2023 | - | 60% |
2 | 4th floor RCC Frame Structure
| Column work for 4th floor will be stated from 2 April and slab will be completed till 14 April | 07/11/2020 | 31/03/2023 | - | 60% |
3 | 5th floor RCC Frame Structure
| Column work for 5th floor will be stated from 16 April and slab will be completed till 28 April | 07/11/2020 | 31/03/2023 | - | 60% |
4 | 6th floor RCC Frame Structure
| Column work for 6th floor will be stated from 30 April and slab will be completed till 15 May | 07/11/2020 | 31/03/2023 | - | 30% |
5 | 7th floor RCC Frame Structure
| 7th Floor RCC Frame Structure will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
6 | 8th floor RCC Frame Structure
| 8th Floor RCC Frame Structure will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
7 | 9th floor RCC Frame Structure
| 8th Floor RCC Frame Structure will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
8 | 10th floor RCC Frame Structure
| 10th Floor RCC Frame Structure will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
9 | 11th floor RCC Frame Structure
| 11th Floor RCC Frame Structure will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
10 | Brick Work
| Brick Work will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 20% |
11 | Flooring Work
| Flooring Work will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
12 | Plastering and Painting Work
| Plastering and Painting Work will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 10% |
13 | Electrification and Firefighting Works
| Electrification and Firefighting Works will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
14 | Utility Installation
| Utility Installation will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
15 | Doors and window Fittings
| Doors and window Fittings will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
16 | Internal Plumbing Works
| Internal Plumbing Works will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
17 | External Sewerage Works
| External Sewerage Works will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |
18 | External Site Development and Approach Road
| External Site Development and Approach Road will be completed within scheduled timeline | 07/11/2020 | 31/03/2023 | - | 1% |