Project Details

PROJECT NAME :  Construction of Barrack for 200 person in PAC Ramnagar
Project Detail / Brief Description:

भू-तल, प्रथम तल, द्वितीय तल, तृतीय तल, चतुर्थ तल, पंचम तल के छत का कार्य पूर्ण। प्रथम तल, द्वितीय तल, तृतीय तल, चतुर्थ तल एवं पंचम तल पर ब्रिक वर्क का कार्य प्रगति में। षष्ठम तल के कालम का कार्य प्रगति में। मु0अ0 (भवन), लो0नि0वि0, लखनऊ द्वारा अपने पत्र संख्या 1271/5बी0पी0-विंग (बी0एम0-15)/2022 दिनांक 20.06.2022 द्वारा अपर पुलिस महानिदेशक उ0प्र0 पुलिस मुख्यालय, लखनऊ को धनावंटन हेतु मांग पत्र प्रेषित है।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Dec/2020 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
5th floor slab will be casted in next 15 days 16/04/2022 30/04/2022 100%
Slab of 4th floor will be casted till 31st March 2 16/03/2022 31/03/2022 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 3rd floor RCC Frame Structure
Slab casting will be completed by 31st March 07/11/2020 31/03/2023 - 60%
2 4th floor RCC Frame Structure
Column work for 4th floor will be stated from 2 April and slab will be completed till 14 April 07/11/2020 31/03/2023 - 60%
3 5th floor RCC Frame Structure
Column work for 5th floor will be stated from 16 April and slab will be completed till 28 April 07/11/2020 31/03/2023 - 60%
4 6th floor RCC Frame Structure
Column work for 6th floor will be stated from 30 April and slab will be completed till 15 May 07/11/2020 31/03/2023 - 30%
5 7th floor RCC Frame Structure
7th Floor RCC Frame Structure will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
6 8th floor RCC Frame Structure
8th Floor RCC Frame Structure will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
7 9th floor RCC Frame Structure
8th Floor RCC Frame Structure will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
8 10th floor RCC Frame Structure
10th Floor RCC Frame Structure will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
9 11th floor RCC Frame Structure
11th Floor RCC Frame Structure will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
10 Brick Work
Brick Work will be completed within scheduled timeline 07/11/2020 31/03/2023 - 20%
11 Flooring Work
Flooring Work will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
12 Plastering and Painting Work
Plastering and Painting Work will be completed within scheduled timeline 07/11/2020 31/03/2023 - 10%
13 Electrification and Firefighting Works
Electrification and Firefighting Works will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
14 Utility Installation
Utility Installation will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
15 Doors and window Fittings
Doors and window Fittings will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
16 Internal Plumbing Works
Internal Plumbing Works will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
17 External Sewerage Works
External Sewerage Works will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%
18 External Site Development and Approach Road
External Site Development and Approach Road will be completed within scheduled timeline 07/11/2020 31/03/2023 - 1%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
1002.55 Lac. 420.63 Lac. 420.63 Lac. 0 Lac. 581.92 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...