PROJECT NAME :  Construction of Shivpur Lahartara (Phulwariya) 04 Lane Road
Project Detail / Brief Description:

भूमि विवाद होने के कारण एवं मार्ग के संरेखण में दो रेलवे उपरिगामी सेतु एवं एक वरूणा नदी पर दीर्घ सेतु का निर्माण सेतु निर्माण निगम द्वारा कराया जा रहा है, जो कि प्रगति में है।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

State Yojana

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 25/Jun/2018 Project Planned Completion Date: 31/Dec/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Earth work
Length 2.85 km completed out of total length 2.85 km
25/06/2018 15/09/2021 - 100%
2 GSB
Length 5.08 km completed out of total length 5.08 km 25/06/2018 19/02/2022 - 100%
3 WMM
Length 5.08 km completed out of total length 5.08 km 25/08/2018 21/02/2022 - 100%
4 DBM
Length 4.98 km completed out of total length 5.08 km 01/10/2018 30/04/2022 - 98%
5 BC
Length 4.26 km completed out of total length 5.08 km 01/06/2020 05/05/2022 - 84%
6 Drain
Length 9.00 Km completed out of total length 10.30 Km 25/06/2018 12/05/2022 - 87%
7 Divider
Length 4.71 km completed out of total length 4.71 km 01/10/2018 12/01/2022 - 100%
8 Boundary Wall
Length 1.80 km completed out of total length 1.85 km 01/10/2018 10/05/2021 - 97%
9 Interlocking Tiles
Length 2.50 km completed out of total length 3.50 km 01/07/2020 11/05/2022 - 71%
10 Box Calvert
3 nos completed out of total 3 nos 01/01/2019 30/04/2022 - 100%
11 Road furniture
0 01/11/2020 15/05/2022 - 20%
12 Retaining wall
8.20 mtr. high return wall completed out of 8.20 mtr. high 27/01/2021 31/08/2021 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
16614 Lac. 13419.24 Lac. 12928.24 Lac. 13419.2 Lac. 17104.96 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...