PROJECT NAME : Construction of Shivpur Lahartara (Phulwariya) 04 Lane Road
Project Detail / Brief Description:
भूमि विवाद होने के कारण एवं मार्ग के संरेखण में दो रेलवे उपरिगामी सेतु एवं एक वरूणा नदी पर दीर्घ सेतु का निर्माण सेतु निर्माण निगम द्वारा कराया जा रहा है, जो कि प्रगति में है।
Project Department:
Public Work Department (PWD)
Associated Yojna Name:
State Yojana
Goals, Objectives and Benefits of Project:
PROJECT MANAGER / INCHARGE
Name
Email
Contact
Designation
Sugreev Ram
pdpwdvns@gmail.com
9415391224
PROJECT DATES
Project Planned Start Date: 25/Jun/2018
Project Planned Completion Date:
31/Dec/2022
Actual Start Date: N/A
Reason for Delay Actual Start Date: N/A
New Revised Completion Date:N/A
Reason for Delay New Revised Completion Date: N/A
15 Days Task
Task Name
Start Date
End Date
Percentage(%)
No Task..
Component Wise Project Progress
Sr.no.
Component Name
Start Date
End Date
Planned Percentage(%)
Actual Percentage(%)
Cumulative Total Progress
Reason for Delay
No Component..
SCHEDULE
Sr.
Milestone
Description
Start Date
Planned Completion Date
Actual Completion Date
Milestone Completion(In %)
1
Earth work
Length 2.85 km completed out of total length 2.85 km
25/06/2018
15/09/2021
-
100%
2
GSB
Length 5.08 km completed out of total length 5.08 km
25/06/2018
19/02/2022
-
100%
3
WMM
Length 5.08 km completed out of total length 5.08 km
25/08/2018
21/02/2022
-
100%
4
DBM
Length 4.98 km completed out of total length 5.08 km
01/10/2018
30/04/2022
-
98%
5
BC
Length 4.26 km completed out of total length 5.08 km
01/06/2020
05/05/2022
-
84%
6
Drain
Length 9.00 Km completed out of total length 10.30 Km
25/06/2018
12/05/2022
-
87%
7
Divider
Length 4.71 km completed out of total length 4.71 km
01/10/2018
12/01/2022
-
100%
8
Boundary Wall
Length 1.80 km completed out of total length 1.85 km
01/10/2018
10/05/2021
-
97%
9
Interlocking Tiles
Length 2.50 km completed out of total length 3.50 km
01/07/2020
11/05/2022
-
71%
10
Box Calvert
3 nos completed out of total 3 nos
01/01/2019
30/04/2022
-
100%
11
Road furniture
0
01/11/2020
15/05/2022
-
20%
12
Retaining wall
8.20 mtr. high return wall completed out of 8.20 mtr. high