Project Details

PROJECT NAME :  Construction of holy path for Kashi Char Dham Yatra, Kashi Vishnu Yatra, and Dwadas Aditya Yatra, Nav Durga Yatra, Ast Bhairav/Nav Gauri Yatra, Ast Vinayak/Vinayak and Dwadas Jyotirling Yatra under the overall tourism development plan in Varanasi
Project Detail / Brief Description:

Work in progress.


Project Department:

Uttar Pradesh Project Corporation Limited

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Vinay Kumar Jain pm3@upprojects.org 8114434325
Raj Nath Yadav pm_3@upprojects.org 9454419141

 PROJECT DATES
Project Planned Start Date: 01/Jul/2022 Project Planned Completion Date: 31/Dec/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Stone Flooring, Interlocking, Road Marking & Information Signage Board
Work in progress. 15/07/2022 15/03/2023 - 65%
2 Entrance Gate, Entrance Stambh (Type-1), Entrance Stambh (Type-2)
Work in progress. 05/10/2022 05/04/2023 - 55%
3 Stone Signage of Destination Milestone/Totem and Stone Information Signage, Way Finders & Directional Signage
Work in progress. 01/01/2023 15/05/2023 - 30%
4 Signage for Dipcting the Historic Significance of Religious Sites.
Work in progress. 01/01/2023 15/05/2023 - 20%
5 Landscape an Horticulture work
Work in progress. 01/04/2023 20/08/2023 - 55%
6 Stone Benches, Lamp Post, Dust Bin and Drinking Water Kiosk
Work in progress. 01/09/2023 15/12/2023 - 55%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
2434.08 Lac. 1942.83 Lac. 1040 Lac. 0 Lac. 1394.08 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...