PROJECT NAME :  Construction work of 143 Rural Drinking Water schemes under Har Ghar Nal Yojana
Project Detail / Brief Description:


Project Department:

Jal Nigam 6th Construction Division

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
S.K. Singh 9473942681 Project Manager

 PROJECT DATES
Project Planned Start Date: 01/Jun/2021 Project Planned Completion Date: 28/Feb/2023
Actual Start Date: 08/Oct/2021 Reason for Delay Actual Start Date: N/A New Revised Completion Date:09/Feb/2024 Reason for Delay New Revised Completion Date: Land Dispute, utility shifting and tree cutting

15 Days Task
 Task Name Start Date End Date Percentage(%)
the target of 15 days is to complete 5 no. of wat 16/08/2022 31/08/2022 20%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 construction of 34 no. rural drinking water schemes under har ghar nal yojana
out of 34 no. of schemes, water supply started in 19 no. of schemes with direct supply of tubewells. 25/03/2022 25/09/2022 - 50%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
42800 Lac. 2428 Lac. 2428 Lac. 0 Lac. 40372 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...