Project Details

PROJECT NAME :  Construction work of 68 Rural Drinking Water schemes under Jal Jeevan Har Ghar Nal Yojana
Project Detail / Brief Description:


Project Department:

Jal Nigam 6th Construction Division

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation

 PROJECT DATES
Project Planned Start Date: 01/Feb/2021 Project Planned Completion Date: 30/Jun/2023
Actual Start Date: 12/Aug/2021 Reason for Delay Actual Start Date: N/A New Revised Completion Date:16/Mar/2024 Reason for Delay New Revised Completion Date: Land dispute , Tree cutting pending and utility shifting

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
No Milestone Assign

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
21241 Lac. 4000 Lac. 20500 Lac. 0 Lac. 741 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...