Project Details

PROJECT NAME :  Establishment of Shooting Range in Varanasi
Project Detail / Brief Description:

work in progress


Project Department:

Uttar Pradesh Rajkiya Nirman Nigam Limited (UPRNNL) Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. B. Singh gmald.bhadohi@gmail.com 8400400488 Project Manager
UPRNN Varanasi Zone gmvns.bhadohi@gmail.com 9919418282

 PROJECT DATES
Project Planned Start Date: 01/Jul/2021 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
work in progress 01/05/2022 15/05/2022 60%
WORK IN PROGRESS 01/05/2022 15/05/2022 20%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 GROUND FLOOR - 50 MTR 13 LANE
FOUNDATION WORK COMPLETED, SUPER STRUCTURE WORK IN PROGRESS. SLAB CASTING WORK IN PROGRESS 31/07/2021 30/09/2022 - 58%
2 FIRST FLOOR
SUPER STRUCTURE WORK IN PROGRESS 30/06/2022 30/09/2022 - 15%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
504 Lac. 287.97 Lac. 201 Lac. 0 Lac. 303 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...