Project Details

PROJECT NAME :  Four Lane Widening of National Highway No.233,PKG-3 (Ghaghra Bridge- Varanasi Division)
Project Detail / Brief Description:

Likely Date of completion - 31.03.2022


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Jan/2016 Project Planned Completion Date: 30/Jun/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
Project of length 42.26 km (out of 59.01 km) has b 16/12/2023 31/12/2023 100%
Project of length 42.26 km (out of 59.01 km) has b 01/12/2022 15/12/2022 100%
Project of length 42.26 km (out of 59.01 km) has b 16/08/2022 31/08/2022 100%
Project of length 42.26 km has been completed on 0 16/06/2022 30/06/2022 100%
Project completed on 02.06.2022. PCC issued. 01/06/2022 15/06/2022 100%
Towards completion of Project. (Except 15.89 km du 01/05/2022 15/05/2022 97%
Towards completion of Project. (Except 15.89 km du 16/04/2022 30/04/2022 97%
Towards completion of Project. (Except 15.89 km l 16/04/2022 30/04/2022 97%
Towards completion of Project. (Except 15.89 km l 01/04/2022 15/04/2022 97%
Towards completion of Project. 01/03/2022 15/03/2022 95%
Towards completion of Project. 16/10/2020 31/10/2020 94%
Towards completion of Project. 01/10/2020 15/10/2020 94%
Towards completion of Project. 16/10/2020 31/10/2020 94%
Towards completion of Project. 01/10/2020 15/10/2020 94%
Towards completion of Project. 16/09/2021 30/09/2021 94%
Towards completion of Project. 16/08/2021 31/08/2021 90%
Towards Schedule completion. 16/08/2021 31/08/2021 94%
Towards Schedule completion. 01/08/2021 15/08/2021 94%
Towards Schedule completion. 16/07/2021 31/07/2021 93%
Towards Schedule completion. 16/03/2021 31/03/2021 91%
Towards Schedule completion. 01/03/2021 15/03/2021 91%
Towards Schedule completion. 16/02/2021 28/02/2021 90%
Towards Schedule completion. 01/02/2021 15/02/2021 90%
Towards completion of Project. 16/02/2021 03/03/2021 90%
Towards completion of Project. 01/01/2021 15/01/2021 89%
Towards completion of Project. 16/12/2020 31/12/2020 88%
Towards completion of Project. 16/11/2020 30/11/2020 88%
Towards completion of Project. 01/11/2020 15/11/2020 87%
Towards completion of Project. 01/10/2020 15/10/2020 0%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Schedule Completion
TaskDescriptionStart Date End DateStatus
Completion Project of length 42.26 km (out of 59.01 km) has been completed on 02.06.2022 (PCC issued) and 16.75 km length de-scoped from the scope of contractor due to non availability of land. At present, Court Case of land acquisition is under sub-judice of Hon'ble High Court, Allahabad 01/01/2016 02/06/2022 100%
Project of length 42.26 km (out of 59.01 km) has been completed on 02.06.2022 (PCC issued) and 16.75 km length de-scoped from the scope of contractor due to non availability of land. At present, Court Case of land acquisition is under sub-judice of Hon'ble High Court, Allahabad 01/01/2016 02/06/2022 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
240528 Lac. 211651 Lac. 211651 Lac. 240528 Lac. 269405 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...