PROJECT NAME :  Overall Tourism Development Work of Panchkoshi Parikrama Yatra (5 Halts)
Project Detail / Brief Description:

Work in progress.


Project Department:

Uttar Pradesh Project Corporation Limited

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Vinay Kumar Jain pm3@upprojects.org 8114434325
Raj Nath Yadav pm_3@upprojects.org 9454419141

 PROJECT DATES
Project Planned Start Date: 01/Jul/2022 Project Planned Completion Date: 31/Dec/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Conservation, Restoration & Development of Structure (Dharmshala)
Work in progress. 20/07/2022 15/04/2023 - 60%
2 Electrification & Lighting of Dharmshala Complexes
Work in progress. 01/12/2022 30/03/2023 - 15%
3 Plumbing & Sanitary with water supply work all complete.
Work in progress. 01/12/2022 10/04/2023 - 15%
4 Way Finder & Directional Signages
Work not started. 05/11/2022 15/03/2023 - 5%
5 Development of Parking Facilities & Street Scape work.
Work in progress. 15/11/2022 20/05/2023 - 10%
6 Public Convenience Amenities & Facilities with Water Kiosk
Work in progress. 10/08/2022 15/01/2023 - 50%
7 Signage for Dipcting the Historic Significance of Religious Sites.
Work in progress. 01/12/2022 20/07/2023 - 15%
8 Stone Signage of Destination Milestone/Totem and Stone Information Signage, Way Finders & Directional Signage
Work not started. 10/12/2022 15/09/2023 - 5%
9 Water Body and Eco-Restoration of Landscape with Construction of Ghat on Varuna River and Horticulture
Work in progress. 15/11/2022 30/06/2023 - 15%
10 Development of QR Code and its Digital Content for URL, IOS and Android Platforms which will provide Directional Information.
Work in progress. 01/07/2023 05/12/2023 - 25%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
3922.47 Lac. 2932.07 Lac. 1760 Lac. 0 Lac. 2162.47 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...