PROJECT NAME :  PMAY Yojana (Site 2) 608 unit, Harhua
Project Detail / Brief Description:

Work has been completed.


Project Department:

Varanasi Development Authority (VDA)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Secretary Varanasi josecy.vsingh@gmail.com
Secretary Varanasi josecy.vsingh@gmail.com
Secretary Varanasi josecy.vsingh@gmail.com

 PROJECT DATES
Project Planned Start Date: 30/May/2018 Project Planned Completion Date: 08/Nov/2021
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Excavation (खुदाई )
COMPLETED ( ब्लॉक ६ से १ तक ) 15/05/2019 01/08/2019 - 100%
2 Footing (फोडेशन वर्क )
COMPLETED (ब्लॉक ६ से १ तक ) 15/11/2019 01/01/2020 - 100%
3 Up to Plinth (टाई बीम)
COMPLETED 02/02/2020 01/03/2020 - 100%
4 RCC Frame Work (आरसीसी फ्रेम वर्क)
Block 6 ground to 3rd floor का कार्य पूर्ण हो चूका है 01/06/2020 15/07/2020 - 100%
5 RCC frame work (आरसीसी फ्रेम वर्क)
Block 5 ground to 3rd floor का कार्य लगभग पूर्ण हो चूका है 15/07/2020 15/09/2020 - 90%
6 Rcc frame Work (आरसीसी फ्रेम वर्क)
Block ground floor columns and slab का कार्य अभी चल रहा है
20/08/2020 20/12/2020 - 15%
7 Brick work (चिनाई कार्य )
Block 6 ground to 3rd floor का कार्य अभी चल रहा है 15/08/2020 15/12/2020 - 15%
8 Brick work (चिनाई कार्य )
Block 5 ground to 3rd floor का कार्य अभी चल रहा है
20/08/2020 20/12/2020 - 15%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
3832.45 Lac. 1803.1 Lac. 1803.1 Lac. 0 Lac. 2029.35 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...