PROJECT NAME :  Work of establishing Driver Training Center in Varanasi District
Project Detail / Brief Description:

Work is completed


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

under road security

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224
S.K. Singh 9450319171 Assistant Engineer

 PROJECT DATES
Project Planned Start Date: 08/Mar/2019 Project Planned Completion Date: 31/Dec/2020
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 आफिस बिल्डिंग एवं ट्रैक का कार्य
कार्य पूर्ण। 08/03/2019 31/12/2020 - 100%
2 GSB
WORK IS COMPLETED 03/06/2020 18/06/2020 - 100%
3 WBM
WORK IS COMPLETED 19/06/2020 15/07/2020 - 100%
4 BASIC STRUCTURE
WORK IS COMPLETED 08/03/2019 24/07/2019 - 100%
5 FINISHING WORK
कार्य पूर्ण। 01/08/2020 31/12/2020 - 100%
6 PQC PAVEMENT
कार्य पूर्ण। 02/09/2020 15/11/2020 - 100%
7 Brick Koba
TaskDescriptionStart Date End DateStatus
TRACK WORK कार्य पूर्ण। 16/11/2020 30/11/2020 100%
Completion of brick koba work 17/09/2020 24/09/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
444.7 Lac. 444.7 Lac. 444.7 Lac. 0 Lac. 0 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...