PROJECT NAME :  Widening & Strengthening of Panchkoshi Parikrama Road in Distt-Varanasi
Project Detail / Brief Description:

Widing & strenthing of panchkoshi parikarma raod in distt- vns


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

State Yojana

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 13/Jul/2018 Project Planned Completion Date: 31/Mar/2021
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Earth work
. 13/07/2018 30/11/2020 - 100%
2 GSB
Length 46.00 km completed out of total length 53.913 km 13/07/2018 30/11/2020 - 95%
3 WMM
Length 39.20 km completed out of total length 39.20 km 10/09/2018 30/11/2020 - 100%
4 DBM
Length 40.90 km completed out of total length 40.90 km 25/11/2018 30/11/2020 - 100%
5 BC
Length 40.90 km completed out of total length 40.90 km 10/12/2018 30/11/2020 - 100%
6 PQC
Length 1.700 km completed out of total length 1.70 km 18/10/2018 30/11/2020 - 100%
7 Interlocking Tiles
Length 45.00 km completed out of total length 53.913 km 10/02/2019 30/11/2020 - 83%
8 RCC U Type Drain
Length 26.00 km completed out of total length 28.60 km 05/11/2018 30/11/2020 - 90%
9 Stablized Soil for Pathway
Length 0.00 km completed out of total length 40.90 km 16/03/2020 30/11/2020 - 0%
10 Culvert (Hume Pipe)
Length 30 nos completed out of total length 40 nos 04/04/2019 30/11/2020 - 75%
11 Culvert (RCC)
भूमि विवाद के कारण कार्य वाधित है। 04/04/2020 30/11/2020 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
9703.88 Lac. 8618.69 Lac. 8618.69 Lac. 0 Lac. 1085.19 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...