Project Details

PROJECT NAME :  Six lane of Varanasi to Aurangabad Section of NH-2 from Km 786.000 to Km 978.400
Project Detail / Brief Description:


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Sep/2011 Project Planned Completion Date: 23/Nov/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
The concessionaire, SIVATPL through EPC contractor 16/09/2022 30/09/2022 79%
The concessionaire, SIVATPL through EPC contractor 01/09/2022 15/09/2022 65%
The concessionaire, SIVATPL through EPC contractor 16/08/2022 31/08/2022 65%
5% of 4.7 Km. of six lane of 1st milestone. 01/08/2022 15/08/2022 5%
5% of 4.7 Km. of six lane of 1st milestone. 16/06/2022 30/06/2022 5%
5% of 4.7 Km. of six lane of 1st milestone. 16/05/2022 31/05/2022 5%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Milestone-1
The concessionaire, SIVATPL through EPC contractor Welspun started the work of six laning of NH-2 with effect from 27.08.2021 27/08/2021 18/11/2023 - 65%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
284800 Lac. 117291 Lac. 167509 Lac. 0 Lac. 117291 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...