PROJECT NAME : 132/33 KV GIS Substation Alaipur Varanasi |
Project Detail / Brief Description: |
Project Department: U.P. Power Transmission Corporation Limited (UPPTCL) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project:
To ensure uninterrupted and quality power supply to Kajjakpura Town Hall Kashi Deenapur Areas |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Mk Agrawal | czedvns@gmail.com | 9415301234 | |
Indrabhan singh | mukesh06kumar@gmail.com | 9415311043 |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/Jan/1970 | Project Planned Completion Date: 31/Mar/2023 | |||||||||||||||||||||
Actual Start Date: N/A | Reason for Delay Actual Start Date: N/A | New Revised Completion Date:N/A | Reason for Delay New Revised Completion Date: N/A |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Laying of U/G cable in HDPE Pipe near railway Und | 01/06/2023 | 15/06/2023 | 100% |
Drilling of hole by HDD Method and laying HDPE Pip | 16/05/2023 | 31/05/2023 | 100% |
Stringing of Over Head Line 33/33 Lattice Tower an | 01/05/2023 | 15/05/2023 | 100% |
All Control pannel & relay panel received and Erec | 01/02/2023 | 15/02/2023 | 100% |
Cable termination kit for jionting of cable receiv | 01/08/2023 | 15/08/2023 | 100% |
33 KV GIS Module has been Received. Errection of 3 | 01/04/2023 | 15/04/2023 | 100% |
33 KV Side Auxilliary Structure has been Erected.E | 01/09/2022 | 15/09/2022 | 100% |
Material for Auxilliary structure,battery set,Eart | 16/08/2022 | 31/08/2022 | 100% |
Stringing of conductor Loc 11 to 17 | 01/08/2023 | 15/08/2023 | 100% |
Erection and stringing of Loc 22 to Loc 24 | 01/08/2022 | 15/08/2022 | 100% |
Supply of 33 Kv GIS Module,Energy meter,Battery sy | 01/08/2023 | 15/08/2023 | 100% |
Supply of 132 KV GIS module has been done. | 16/07/2023 | 31/07/2023 | 100% |
Transformer Plinth work is in Progress.Auxiliary s | 01/08/2023 | 15/08/2023 | 100% |
completed. | 16/05/2023 | 31/05/2023 | 100% |
Erection of Tower no 6,7,8,9,10. | 01/08/2023 | 15/08/2023 | 100% |
Erection of 6 No Tower has been done during this p | 01/05/2023 | 15/05/2023 | 100% |
Pile foundation work started on Loc No 33 .Minimum | 01/08/2023 | 15/08/2023 | 100% |
The Boundary wall work will be completed by 95%. T | 16/07/2023 | 31/07/2023 | 100% |
The Underground Cables will be shifted to the new | 16/07/2023 | 31/07/2023 | 100% |
Earth resistivity test and Topography. | 16/07/2023 | 31/07/2023 | 100% |
The boundry wall will be completed except the port | 01/08/2023 | 15/08/2023 | 100% |
Left over work of Shifting of ug cable,Transformer | 01/01/2021 | 15/01/2021 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Handover of land from Nagar Nigam, Completion of Boundary Wall and Shifting of underground discom cables. | Work completed. | 08/01/2020 | 30/12/2022 | - | 100% |
2 | Soil testing, Earth resistivity test, Topography & layout finalization . | Work completed.Project completed. | 19/10/2020 | 02/08/2023 | - | 100% |
3 | Construction of 132KV Shahupuri - Sarnath (132KV) LILO @ Alaipur. | Work has been completed and Line charged . 132 KV Sarnath-Alaipur line charged at 22:57 hrs dt 01.08.2023. and 132 KV sahupuri-Alaipur line charged at 00:52 hrs on dt 02.08.2023. | 17/03/2021 | 02/08/2023 | - | 100% |
4 | Civil works | Work has been completed. | 15/11/2020 | 02/08/2023 | - | 100% |
5 | Electrical work Part A | Work completed. Substation charged. | 01/05/2021 | 02/08/2023 | - | 100% |
6 | Electrical work Part B | Work has been completed S/S charged. | 21/05/2021 | 02/08/2023 | - | 100% |
7 | Electrical work Part C | Work completed Substation charged. | 05/06/2021 | 02/08/2023 | - | 100% |
8 | Installationof fire fighting equipments | Work completed S/S Charged. | 15/05/2021 | 02/08/2023 | - | 100% |
9 | Construction of Cable Trenches for Underground Power/Control Cables. | Work completed. S/S charged. | 01/06/2021 | 02/08/2023 | - | 100% |
10 | Miscellaneous leftover works. | Work completed S/S Charged. | 01/09/2021 | 02/08/2023 | - | 100% |
11 | Testing and Energization | Work completed S/S charged. | 16/09/2020 | 02/08/2023 | - | 100% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Released Budget(In Lac) | Expenditure till date (In Lac) C | Total Revised Budget (In Lac)B | Balance Fund (In Lac) (A+B-C) |
0 Lac. | 0 Lac. | 0 Lac. | 0 Lac. | 0 Lac. |
BUDGET RECEIVED IN INSTALLMENT | ||||
---|---|---|---|---|
Sr.No. | Installment Amount (In Lac) | Amount Recived Date | Utilization certificate(UC) | |
No Project Budget Recived in Installment... |