PROJECT NAME :  132/33 KV GIS Substation Alaipur Varanasi
Project Detail / Brief Description:


Project Department:

U.P. Power Transmission Corporation Limited (UPPTCL)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

To ensure uninterrupted and quality power supply to Kajjakpura Town Hall Kashi Deenapur Areas


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Mk Agrawal czedvns@gmail.com 9415301234
Indrabhan singh mukesh06kumar@gmail.com 9415311043

 PROJECT DATES
Project Planned Start Date: 01/Jan/1970 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
Laying of U/G cable in HDPE Pipe near railway Und 01/06/2023 15/06/2023 100%
Drilling of hole by HDD Method and laying HDPE Pip 16/05/2023 31/05/2023 100%
Stringing of Over Head Line 33/33 Lattice Tower an 01/05/2023 15/05/2023 100%
All Control pannel & relay panel received and Erec 01/02/2023 15/02/2023 100%
Cable termination kit for jionting of cable receiv 01/08/2023 15/08/2023 100%
33 KV GIS Module has been Received. Errection of 3 01/04/2023 15/04/2023 100%
33 KV Side Auxilliary Structure has been Erected.E 01/09/2022 15/09/2022 100%
Material for Auxilliary structure,battery set,Eart 16/08/2022 31/08/2022 100%
Stringing of conductor Loc 11 to 17 01/08/2023 15/08/2023 100%
Erection and stringing of Loc 22 to Loc 24 01/08/2022 15/08/2022 100%
Supply of 33 Kv GIS Module,Energy meter,Battery sy 01/08/2023 15/08/2023 100%
Supply of 132 KV GIS module has been done. 16/07/2023 31/07/2023 100%
Transformer Plinth work is in Progress.Auxiliary s 01/08/2023 15/08/2023 100%
completed. 16/05/2023 31/05/2023 100%
Erection of Tower no 6,7,8,9,10. 01/08/2023 15/08/2023 100%
Erection of 6 No Tower has been done during this p 01/05/2023 15/05/2023 100%
Pile foundation work started on Loc No 33 .Minimum 01/08/2023 15/08/2023 100%
The Boundary wall work will be completed by 95%. T 16/07/2023 31/07/2023 100%
The Underground Cables will be shifted to the new 16/07/2023 31/07/2023 100%
Earth resistivity test and Topography. 16/07/2023 31/07/2023 100%
The boundry wall will be completed except the port 01/08/2023 15/08/2023 100%
Left over work of Shifting of ug cable,Transformer 01/01/2021 15/01/2021 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Handover of land from Nagar Nigam, Completion of Boundary Wall and Shifting of underground discom cables.
Work completed. 08/01/2020 30/12/2022 - 100%
2 Soil testing, Earth resistivity test, Topography & layout finalization .
Work completed.Project completed. 19/10/2020 02/08/2023 - 100%
3 Construction of 132KV Shahupuri - Sarnath (132KV) LILO @ Alaipur.
Work has been completed and Line charged . 132 KV Sarnath-Alaipur line charged at 22:57 hrs dt 01.08.2023. and 132 KV sahupuri-Alaipur line charged at 00:52 hrs on dt 02.08.2023. 17/03/2021 02/08/2023 - 100%
4 Civil works
Work has been completed. 15/11/2020 02/08/2023 - 100%
5 Electrical work Part A
Work completed. Substation charged. 01/05/2021 02/08/2023 - 100%
6 Electrical work Part B
Work has been completed S/S charged. 21/05/2021 02/08/2023 - 100%
7 Electrical work Part C
Work completed Substation charged. 05/06/2021 02/08/2023 - 100%
8 Installationof fire fighting equipments
Work completed S/S Charged. 15/05/2021 02/08/2023 - 100%
9 Construction of Cable Trenches for Underground Power/Control Cables.
Work completed. S/S charged. 01/06/2021 02/08/2023 - 100%
10 Miscellaneous leftover works.
Work completed S/S Charged. 01/09/2021 02/08/2023 - 100%
11 Testing and Energization
Work completed S/S charged. 16/09/2020 02/08/2023 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
0 Lac. 0 Lac. 0 Lac. 0 Lac. 0 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...