PROJECT NAME :  Construction of NH-29 Bypass Varanasi Ring Road,Phase-2, PKG-2
Project Detail / Brief Description:

Part of Varanasi Ring Road connecting NH-29 at Village - Sandaha, Dist- Varanasi to NH-2 at Village - Revasa in Dist.- Chandauli of Uttar Pradesh. Likely Date of Completed Dec, 2022


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Decongetor of traffic coming from NH-2,NH-56,NH-233 and NH-29 by providing bypass


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 14/Feb/2019 Project Planned Completion Date: 13/Feb/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
Towards completion of Mile Stone-II 01/10/2020 15/10/2020 34%
Towards completion of Mile Stone-II 16/09/2021 30/09/2021 31%
Towards completion of Mile Stone-II 16/08/2021 31/08/2021 30%
Towards completion of Mile Stone-II 01/08/2021 15/08/2021 30%
Towards completion of Mile Stone-II 16/07/2021 31/07/2021 29%
Towards completion of Mile Stone-II 16/03/2021 31/03/2021 20%
Towards completion of Mile Stone-II 01/03/2021 15/03/2021 19%
Towards completion of Mile Stone-II 16/02/2021 28/02/2021 18%
Towards completion of Mile Stone-II 01/02/2021 15/02/2021 16%
Towards achievement of Milestone-I 01/01/2021 15/01/2021 13%
Towards achievement of Milestone-I 16/12/2020 31/12/2020 11%
Towards achievement of Milestone-I 16/12/2020 31/12/2020 11%
Towards achievement of Milestone-I 16/11/2020 30/11/2020 10%
Towards achievement of Milestone-I 01/11/2020 15/11/2020 9%
Towards completion of Mile Stone-I 01/10/2020 15/10/2020 0%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Milestone - I
IN PROGRESS 14/02/2019 13/08/2019 - 10%
2 Milestone - II
IN PROGRESS 14/02/2019 14/02/2020 - 30%
3 Milestone - III
IN PROGRESS 14/02/2019 16/08/2021 - 60%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
156311 Lac. 82694 Lac. 82694 Lac. 156311 Lac. 229928 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...