Project Details

PROJECT NAME :  Construction of 80 Nos Residential Flats at BHU Varanasi
Project Detail / Brief Description:

Residential flats for BHU faculties. Final cleaning, repairs and touch ups under progress.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Residential flats for BHU professors


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 06/Aug/2018 Project Planned Completion Date: 31/Oct/2020
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
final cleaning, testing, touch ups 01/02/2021 15/02/2021 50%
Final inside finishing under progress. 01/02/2021 15/02/2021 100%
external putty & painting & external development 01/02/2021 15/02/2021 100%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 8th and final mile stone
work completed except final cleaning and touch ups. 01/06/2020 28/02/2021 - 99%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
6063 Lac. 3980 Lac. 3948 Lac. 0 Lac. 2115 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...




Back