L O A D I N G
Back     

Project Details

PROJECT NAME :  City Gas Distribution Varanasi
Project Detail / Brief Description:

GAIL (India) Limited Authorized to create piped Natural gas network to households and CNG stations to supply economically, green fuel to vehicles in Varanasi City. Status as on date; Total GI infrastructure created- 62715 Nos Total PNG Customers:24444 Nos Total Commercial Customers: 65 Nos Total Industrial Customers: 12 Nos Total CNG station operation: 20 nos Additional CNG Station work in progress: 19 nos Further GAIL is expending in other areas


Project Department:

Gas Authority of India Limited (GAIL)

Associated Yojna Name:

Pradhan Mantri Urja Ganga Pariyojana

Goals, Objectives and Benefits of Project:

With an aim to provide uninterrupted access of cleaner and quality energy to Eastern & North Eastern part of the country, gas pipeline projects Jagdishpur – Haldia & Bokaro – Dhamra/ Barauni- Guwahati Pipeline Project (JHBDPL/BGPL) popularly known as the Pradhan Mantri Urja Ganga (PMUG), of total length of 3291 Km are being executed at a cost of approx. Rs. 13,000 Crore.
Government of India is providing a Capital Grant of Rs 5,176 Crores (40% of the project cost) for timely completion of the project by 2020. This pipeline project will cater to the energy requirements of the States of Uttar Pradesh, Bihar, Jharkhand, West Bengal, Odisha and Assamcovering 70 Districts and 3150 Villages.
Along with development of the JHBDPL project, six (06) City Gas Distribution Network (CGD) projects viz Varanasi, Patna, Jamshedpur, Ranchi, Bhubaneswar and Cuttack en-route of pipeline are also being executed. In addition, 15 new Geographical Areas covering 34 districts en-route of Urja Ganga project have been offered for award of CGD projects under the ongoing 9th CGD bidding round.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
N. K. Dwivedi nkdwivedi@gail.co.in 9999037537 Chief Manager(PROJECT-CGD)

 PROJECT DATES
Project Planned Start Date: 30/Apr/2017 Project Planned Completion Date: 31/Mar/2023
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Laying of steel pipeline 89 km
TaskDescriptionStart Date End DateStatus
CUMULATIVE STEEL LAYING -75KM CUMULATIVE STEEL PIPE LAYING TARGET-75.60 KM,ACHIEVED 84 KM 01/04/2018 17/12/2022 100%
LAYING CUMMULATIVE 89 KM .Completed. Target achieved 117% 01/04/2018 11/12/2023 - 100%
2 Laying of MDPE Pipline-694 Km
Cumulative Laying of Different Size of MDPE Pipeline-Total Laid -843 Km. 01/04/2018 11/12/2023 - 99%
3 GI Infrasture-40211
CUMULATIVE GI INFRASTRUCTURE-72007 ACHIEVED AS ON DATE against the target of 40211 nos. 01/04/2018 11/12/2023 - 100%
4 CNG Stations-39
39 CNG Station mechanically completed, out of which 24 are in operation, 01/04/2018 11/12/2023 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
34515 Lac. 34058 Lac. 27890 Lac. 0 Lac. 6625 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...




Back