PROJECT NAME : City Gas Distribution Varanasi |
Project Detail / Brief Description:
GAIL (India) Limited Authorized to create piped Natural gas network to households and CNG stations to supply economically, green fuel to vehicles in Varanasi City. Status as on date; Total GI infrastructure created- 62715 Nos Total PNG Customers:24444 Nos Total Commercial Customers: 65 Nos Total Industrial Customers: 12 Nos Total CNG station operation: 20 nos Additional CNG Station work in progress: 19 nos Further GAIL is expending in other areas |
Project Department: Gas Authority of India Limited (GAIL) |
Associated Yojna Name: Pradhan Mantri Urja Ganga Pariyojana |
||
Goals, Objectives and Benefits of Project:
With an aim to provide uninterrupted access of cleaner and quality energy to Eastern & North Eastern part of the country, gas pipeline projects Jagdishpur – Haldia & Bokaro – Dhamra/ Barauni- Guwahati Pipeline Project (JHBDPL/BGPL) popularly known as the Pradhan Mantri Urja Ganga (PMUG), of total length of 3291 Km are being executed at a cost of approx. Rs. 13,000 Crore. |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
N. K. Dwivedi | nkdwivedi@gail.co.in | 9999037537 | Chief Manager(PROJECT-CGD) |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 30/Apr/2017 | Project Planned Completion Date: 31/Mar/2023 | |||||||||||||||||||||
Actual Start Date: N/A | Reason for Delay Actual Start Date: N/A | New Revised Completion Date:N/A | Reason for Delay New Revised Completion Date: N/A |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | ||||||||||
1 | Laying of steel pipeline 89 km
| LAYING CUMMULATIVE 89 KM .Completed. Target achieved 117% | 01/04/2018 | 11/12/2023 | - | 100% | ||||||||||
2 | Laying of MDPE Pipline-694 Km | Cumulative Laying of Different Size of MDPE Pipeline-Total Laid -843 Km. | 01/04/2018 | 11/12/2023 | - | 99% | ||||||||||
3 | GI Infrasture-40211 | CUMULATIVE GI INFRASTRUCTURE-72007 ACHIEVED AS ON DATE against the target of 40211 nos. | 01/04/2018 | 11/12/2023 | - | 100% | ||||||||||
4 | CNG Stations-39 | 39 CNG Station mechanically completed, out of which 24 are in operation, | 01/04/2018 | 11/12/2023 | - | 100% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Released Budget(In Lac) | Expenditure till date (In Lac) C | Total Revised Budget (In Lac)B | Balance Fund (In Lac) (A+B-C) |
34515 Lac. | 34058 Lac. | 27890 Lac. | 0 Lac. | 6625 Lac. |
BUDGET RECEIVED IN INSTALLMENT | ||||
---|---|---|---|---|
Sr.No. | Installment Amount (In Lac) | Amount Recived Date | Utilization certificate(UC) | |
No Project Budget Recived in Installment... |