PROJECT NAME :  Construction of J.D Residence at Sundarpur
Project Detail / Brief Description:

Construction of joint director, HOD & Type - 3, Type - 01 Residence.


Project Department:

Uttar Pradesh Project Corporation Limited

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Residential facilities for employee


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Vinay Kumar Jain pm3@upprojects.org 8114434325

 PROJECT DATES
Project Planned Start Date: 13/Sep/2019 Project Planned Completion Date: 28/Feb/2021
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Construction of J.D. Residence
J.D. Residence slab work completed. 01/09/2019 31/12/2020 - 35%
2 Construction of H.O.D. Residence
H.O.D. Residence slab work is on progress. 01/09/2019 31/12/2020 - 30%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
96.63 Lac. 96.63 Lac. 52 Lac. 0 Lac. 44.63 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...