Project Details

PROJECT NAME :  Construction of official buliding for Economic Offence Research Organisation Unit in Varanasi
Project Detail / Brief Description:

द्वितीय तल का कार्य प्रगति में।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Jul/2021 Project Planned Completion Date: 31/Dec/2022
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
BRICK WORK in ground floor has been completed and 16/03/2022 31/03/2022 33%
Slab casting of first floor will be completed befo 16/03/2022 31/03/2022 50%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 EXCAVATION WORK
EXCAVATION WORK HAS BEEN COMPLETED 17/08/2021 10/09/2021 - 100%
2 PCC AND FOUNDATION WORKS
PCC AND FOUNDATION WORKS HAS BEEN COMPLETED 10/09/2021 22/12/2021 - 100%
3 RCC FRAME STRUCTURE WORK 1st Floor, 2nd Floor and 3rd floor
RCC FRAME STRUCTURE WORK IS IN PROGRESS 23/12/2021 01/05/2022 - 30%
4 BRICK WORK
BRICK WORK IS IN PROGRESS 15/12/2021 15/07/2022 - 35%
5 PLUMBING, SANITARY AND FINISHING WORK
FINISHING WORK WILL STRAT AS PER SCHEDULE DATE 31/03/2022 17/06/2022 - 1%
6 External site development and approach Road Work
External site development and approach Road Work will be completed as per schedule 01/06/2022 17/06/2022 - 1%
7 Utility Shifting to be done by UPPCL
Utility Shifting to be done by UPPCL 13/04/2022 22/08/2022 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
174.34 Lac. 118.86 Lac. 44 Lac. 0 Lac. 130.34 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...