PROJECT NAME :  Construction of 48 Nos Awas under Asara Awas Yojna Akatha Varanasi
Project Detail / Brief Description:

Construction of 48 Nos. Relocation Houses under Aasra Awas Yojna at Akatha, Varanasi


Project Department:

Construction & Design Services (C&DS) Unit-24,U.P Jal Nigam

Associated Yojna Name:

Aasra Awas Yojna

Goals, Objectives and Benefits of Project:

1- To provide the housing units to poor families, residing in slums & minority dominated colonies of urban areas.

2- The scheme keen on providing all kinds of initiatives to develop the living standards of the poor people.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Arvind Kumar gourarvind48@ gmail.com 9628676490 Resident Engineer
Ekank Tanwar pm24.vns@gmail.com 9627173063

 PROJECT DATES
Project Planned Start Date: 01/Nov/2015 Project Planned Completion Date: 31/Mar/2018
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Construction of 48 Nos. Relocation Houses
Due to non availability of funds, works is yet held up. 07/11/2015 31/03/2018 - 90%
2 Construction of Boundary Wall
After availability of funds, remaining work will be taken up 15/11/2015 31/01/2018 - 95%
3 Infrastructure Works
After availability of funds, remaining works will be taken up 01/04/2016 31/03/2018 - 50%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
177.84 Lac. 0 Lac. 177.84 Lac. 73.25 Lac. 73.25 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...