PROJECT NAME : Urban Revitalization of Road and Junctions Improvement Project in ABD area Phase 2
Project Detail / Brief Description:
Road construction work is completed at Beniabag. Scope of work has been reduced
Project Department:
Smart City Varanasi
Associated Yojna Name:
Smart City Mission
Goals, Objectives and Benefits of Project:
1.Total Road length covered 10.5 Km and 8 Junctions.
2.Modification of the junctions with improved geometry.
3.Table top crossing, kerbs as per turning raidus, yellow box junctions and road safety features etc. on the junctions.
4.Pedestrain Pathways along the roads.
5.Demarcation of lanes and Carriage-way.
6.Kerb channel drain, road edge drain connecting with existing storm water infrastructure.
7.Street furniture such as benches, dust-bins etc.
8.Visitor facilities:information kiosk, drinking water kiosks, bio-toilets etc.
9.Other features: bollards, ramps for physically challenged, landscaping features, plantations with tree-guards etc.
PROJECT MANAGER / INCHARGE
Name
Email
Contact
Designation
Rajesh Kumar Trivedi
rajesh.trivedi@repl.global
8840994640
Construction Manager, PMC-VSCL
Sunil Kumar
mail@varanasismartcity.gov.in
PROJECT DATES
Project Planned Start Date: 01/Dec/2021
Project Planned Completion Date:
30/Nov/2022
Actual Start Date: N/A
Reason for Delay Actual Start Date: N/A
New Revised Completion Date:N/A
Reason for Delay New Revised Completion Date: N/A
15 Days Task
Task Name
Start Date
End Date
Percentage(%)
No Task..
Component Wise Project Progress
Sr.no.
Component Name
Start Date
End Date
Planned Percentage(%)
Actual Percentage(%)
Cumulative Total Progress
Reason for Delay
No Component..
SCHEDULE
Sr.
Milestone
Description
Start Date
Planned Completion Date
Actual Completion Date
Milestone Completion(In %)
1
Sampling work
Sampling work completed.
01/08/2020
09/08/2020
-
100%
2
CC road from Maidagin to Gowdowlia
WIP
02/01/2021
15/02/2022
-
85%
3
Cobble stone laying Maidagin to Godowlia
WIP
01/03/2021
30/09/2021
-
35%
4
Bituman Road work and KC drain Gowdolia to sonarpura
WIP
01/03/2021
30/09/2021
-
80%
5
Road Marking and traffic feature Gowdolia to sonarpura
work is in progress
01/04/2021
30/09/2021
-
30%
6
Bitumen Road constriction and KC drain from sonarpura to Bhelupur
wip
01/03/2021
30/09/2021
-
90%
7
Road Marking and traffic feature sonarpura to Bhelupur