Project Details

PROJECT NAME :  Rail Over Bridge at Babatpur - Kapsethi - Bhadohi Road at Railway Crossing No. 21A/2T in Distt. Varanasi
Project Detail / Brief Description:

Construction of rail over bridge at Babatpur - Kapsethi - road at railway crossing no. 21A/2T


Project Department:

U.P. State Bridge Corporation Ltd. - Varanasi Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

1. To decongestant Varanasi City in general and vehicles traveling on Babatpur to Bhadohi.
2. To save waiting time at railway crossings.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
SANTOSH KUMAR NIRANJAN bcuvaranasi@gmail.com 8765973499 Dy. Project Manager

 PROJECT DATES
Project Planned Start Date: 01/Mar/2019 Project Planned Completion Date: 30/Jun/2021
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
कार्य पूर्ण 01/03/2022 15/03/2022 0%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 फ़ाउंडेशन
कार्य पूर्ण है 01/03/2019 31/08/2020 - 100%
2 सब स्टृक्चर
कार्य पूर्ण है 01/07/2019 30/11/2020 - 100%
3 सुपर स्ट्रक्चर
कार्य पूर्ण है 01/12/2019 28/02/2021 - 100%
4 आर0 ई0 वाल
कार्य पूर्ण है 01/06/2020 31/05/2021 - 100%
5 सर्विस रोड
कार्य पूर्ण है 01/03/2021 30/06/2021 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
3810.5 Lac. 3810.5 Lac. 2806.92 Lac. 0 Lac. 1003.58 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...