PROJECT NAME : Redevelopment of Wards of Old Kashi-Kaal Bhairav Ward
Project Detail / Brief Description:
Improvise infrastructure such as water supply, sewerage system, artistic painting and efficient lighting of the ward for better environmental quality while preserving the local culture and heritage.
Project Department:
Smart City Varanasi
Associated Yojna Name:
Smart City Mission
Goals, Objectives and Benefits of Project:
1.Retrofitting of the Old Kashi Streets – Chunar Stone flooring,Strengthening of street service infrastructure
2.Replacement of Sewerage Line
3.Replacement of water supply line
4.Provision of Ducks for laying services in future.
5.Artisting painting work on property wall
6.Preserving the character of Old streets of Kashi
PROJECT MANAGER / INCHARGE
Name
Email
Contact
Designation
Rajesh Kumar Trivedi
rajesh.trivedi@repl.global
8840994640
Construction Manager, PMC-VSCL
Sunil Kumar
mail@varanasismartcity.gov.in
PROJECT DATES
Project Planned Start Date: 12/Mar/2020
Project Planned Completion Date:
30/Sep/2021
Actual Start Date: N/A
Reason for Delay Actual Start Date: N/A
New Revised Completion Date:N/A
Reason for Delay New Revised Completion Date: N/A
15 Days Task
Task Name
Start Date
End Date
Percentage(%)
As per site requirement materials would be procure
16/10/2020
31/10/2020
70%
Sewer line and water supply work in progress.
16/10/2020
31/10/2020
40%
Component Wise Project Progress
Sr.no.
Component Name
Start Date
End Date
Planned Percentage(%)
Actual Percentage(%)
Cumulative Total Progress
Reason for Delay
No Component..
SCHEDULE
Sr.
Milestone
Description
Start Date
Planned Completion Date
Actual Completion Date
Milestone Completion(In %)
1
Mobilization of manpower and T&P
.Completed.
06/06/2020
30/09/2020
-
100%
2
Arrangement of materials as RCC, DWC, & DI Pipes for 500 mtr
completed
07/06/2020
30/08/2020
-
100%
3
Laying of sewer line and water line in 500 mtr patch
Sewer line, Chamber, water line domestic connection completed.
09/06/2020
30/10/2020
-
100%
4
Procurement of materials of RCC, DWC, & DI Pipes for 2000 mtr
WIP
01/09/2020
28/02/2021
-
70%
5
Laying of Sewer line and Water line from 501 mtr to 2000 mtr
Sewer line -1800 mtr, water supply - 1500 mtr completed.