PROJECT NAME :  Development and Beautification of Chakra and Sonbhadra Pond
Project Detail / Brief Description:

Restoration of the waterbodies as integral natural assets, aesthetical improvement to make it feasible as a potential public area for recreational activities without putting a negative impact on the pond.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:

1. Entrance Plaza with Ticketing Provision.
2. Access and Play area for Differently-abled persons.
3. Aerated fountain and water plants to keep water fresh.
4. Open Gym, Kids play area, Sand pits.
5. Sitting area, Pergola, Gazebo in viewing areas.
6. Boating facilities.
7. Boundary Wall with Artistic & Mural Painting.
8. Landscaping - Jogging Path, Vegetation and Tree Plantation.
9. Directional Signage's.
10.Drinking Water, Public Convince, Adequate Garbage bins.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
D.P. Mishra deo.mishra@repl.global 9990065441 Infrastructure Specialist, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 26/Dec/2019 Project Planned Completion Date: 30/Jun/2021
Actual Start Date: N/A Reason for Delay Actual Start Date: N/A New Revised Completion Date:N/A Reason for Delay New Revised Completion Date: N/A

15 Days Task
 Task Name Start Date End Date Percentage(%)
Chakra pond Excavation of footing in progress 16/10/2020 31/10/2020 40%
Chakra pond Footing, plinth beam, column, brick, 16/10/2020 31/10/2020 85%
Boundary wall work in progress in Chakra. 16/10/2020 31/10/2020 80%
Dewatering has been done on Chakra pond 16/10/2020 31/10/2020 75%
Cleaning of Chakra Pond has been done. 16/10/2020 31/10/2020 90%
Chakra pond dismantling of encroachment, removing 16/10/2020 31/10/2020 85%


SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Cleaning of Ponds
Cleaning of Chakra Pond has been done.
Cleaning of Sonbhadra Pond has been completed 95%
03/01/2020 31/01/2021 - 100%
2 Dismantling and Removing of Encroachment / Waste
Chakra pond dismantling of encroachment, removing and shifting of waste Material have done.
09/01/2020 31/01/2021 - 100%
3 Dewatering
Dewatering has been done on Chakra pond and sonbhadra pond 23/02/2020 28/02/2021 - 100%
4 Boundary Wall Construction
Boundary wall work has been done. 31/01/2020 31/01/2021 - 100%
5 Toilet Work
Chakra pond
Toilet block have been constructed and sanitary and plumbing to be done.
25/07/2020 15/09/2021 - 75%
6 Pathway with railing
Pathway with railing work has been done at chakra pond. In sonbhadra Pathway work is in progress. 01/07/2021 31/08/2021 - 65%
7 construciton of view area
Construction of view area has been completed at chakara and in sonbhadra pond construction of view areae is in progress 01/07/2021 31/08/2021 - 70%
8 Lighting work
Installation of lighting work are in progress 01/07/2021 31/08/2021 - 50%
9 Stone Pitching work
Stone Pitching work has been completed 01/03/2021 31/07/2021 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Released Budget(In Lac) Expenditure till date (In Lac) C Total Revised Budget (In Lac)B Balance Fund (In Lac) (A+B-C)
397 Lac. 397 Lac. 204 Lac. 0 Lac. 193 Lac.
BUDGET RECEIVED IN INSTALLMENT
Sr.No. Installment Amount (In Lac) Amount Recived Date Utilization certificate(UC)
No Project Budget Recived in Installment...