PROJECT NAME : Development and Beautification of Chakra and Sonbhadra Pond
Project Detail / Brief Description:
Restoration of the waterbodies as integral natural assets, aesthetical improvement to make it feasible as a potential public area for recreational activities without putting a negative impact on the pond.
Project Department:
Smart City Varanasi
Associated Yojna Name:
Smart City Mission
Goals, Objectives and Benefits of Project:
1. Entrance Plaza with Ticketing Provision.
2. Access and Play area for Differently-abled persons.
3. Aerated fountain and water plants to keep water fresh.
4. Open Gym, Kids play area, Sand pits.
5. Sitting area, Pergola, Gazebo in viewing areas.
6. Boating facilities.
7. Boundary Wall with Artistic & Mural Painting.
8. Landscaping - Jogging Path, Vegetation and Tree Plantation.
9. Directional Signage's.
10.Drinking Water, Public Convince, Adequate Garbage bins.
PROJECT MANAGER / INCHARGE
Name
Email
Contact
Designation
D.P. Mishra
deo.mishra@repl.global
9990065441
Infrastructure Specialist, PMC-VSCL
Sunil Kumar
mail@varanasismartcity.gov.in
PROJECT DATES
Project Planned Start Date: 26/Dec/2019
Project Planned Completion Date:
30/Jun/2021
Actual Start Date: N/A
Reason for Delay Actual Start Date: N/A
New Revised Completion Date:N/A
Reason for Delay New Revised Completion Date: N/A
15 Days Task
Task Name
Start Date
End Date
Percentage(%)
Chakra pond
Excavation of footing in progress
16/10/2020
31/10/2020
40%
Chakra pond
Footing, plinth beam, column, brick,
16/10/2020
31/10/2020
85%
Boundary wall work in progress in Chakra.
16/10/2020
31/10/2020
80%
Dewatering has been done on Chakra pond
16/10/2020
31/10/2020
75%
Cleaning of Chakra Pond has been done.
16/10/2020
31/10/2020
90%
Chakra pond dismantling of encroachment, removing
16/10/2020
31/10/2020
85%
Component Wise Project Progress
Sr.no.
Component Name
Start Date
End Date
Planned Percentage(%)
Actual Percentage(%)
Cumulative Total Progress
Reason for Delay
No Component..
SCHEDULE
Sr.
Milestone
Description
Start Date
Planned Completion Date
Actual Completion Date
Milestone Completion(In %)
1
Cleaning of Ponds
Cleaning of Chakra Pond has been done.
Cleaning of Sonbhadra Pond has been completed 95%
03/01/2020
31/01/2021
-
100%
2
Dismantling and Removing of Encroachment / Waste
Chakra pond dismantling of encroachment, removing and shifting of waste Material have done.
09/01/2020
31/01/2021
-
100%
3
Dewatering
Dewatering has been done on Chakra pond and sonbhadra pond
23/02/2020
28/02/2021
-
100%
4
Boundary Wall Construction
Boundary wall work has been done.
31/01/2020
31/01/2021
-
100%
5
Toilet Work
Chakra pond
Toilet block have been constructed and sanitary and plumbing to be done.
25/07/2020
15/09/2021
-
75%
6
Pathway with railing
Pathway with railing work has been done at chakra pond. In sonbhadra Pathway work is in progress.
01/07/2021
31/08/2021
-
65%
7
construciton of view area
Construction of view area has been completed at chakara and in sonbhadra pond construction of view areae is in progress