PROJECT NAME : International Girls Hostel[G+10] |
Project Detail / Brief Description:
This is a Ground + 10 floors building for International Girls students being constructed in BHU, Varanasi campus. The building consists of 200 nos. double bedded rooms with all modular Kitchen ,furniture, etc. from 1st to 10th floors. The building also has 2 nos. warden quarters at ground floor, common kitchen laundromat, Library, Gym, Yoga hall, offices, pantry, and other related services of civil and electricals. |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/Jul/2021 | Project Planned Completion Date: 31/Jan/2023 | |||||||||||||||||||||
Actual Start Date: N/A | Reason for Delay Actual Start Date: N/A | New Revised Completion Date:N/A | Reason for Delay New Revised Completion Date: N/A |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Wall tile work External plaster S.S. railing wo | 16/12/2022 | 31/12/2022 | 5% |
1. Granite & tiling work in 8th & 9th floor is in | 16/09/2022 | 30/09/2022 | 100% |
1. Tiling and granite work on 8th & 9th Floor is i | 16/09/2022 | 30/09/2022 | 100% |
Flooring work at 8th & 9th floor External plaster | 16/09/2022 | 30/09/2022 | 100% |
Flooring work at 7th and 8th floor external plast | 16/08/2022 | 31/08/2022 | 100% |
Tile work in rooms and Granite work in corridors. | 16/05/2022 | 31/05/2022 | 100% |
RCC slab upto floor level 12 (Terrace level) Bric | 16/04/2022 | 30/04/2022 | 100% |
RCC slab upto floor level 12 (Terrace level) Bric | 01/04/2022 | 15/04/2022 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | First Mile Stone | (a) RCC of Foundation upto plinth level & other works upto plinth level. (b) Procurement of complete shuttering materials including beams, slabs, walls, props, accessories etc. to cover two floors at a time for both the blocks. Column shutterings of atleast 45 Columns (proportionately as per size of columns). (c) Submission & approval of all shop drawings & approval of specialized agencies within one month from date of start. B- Activity completion of E&M work: (a) Submission of eligibility | 01/07/2020 | 30/09/2020 | - | 100% |
2 | Second Mile Stone | (a) RCC slab upto floor level 5 (b) Brick/Block work upto level 3 (c) Flooring work upto floor level 2 B- Activity completion of E&M work: (a) Wall conduiting upto floor level 5 (b) Wall conduiting, fixing of switch, socket boxes and DBs upto floor level 2 (c) Making of holes in toilets, rooms, kitchen, fire fighting and exhaust etc. upto floor level 2 | 01/10/2020 | 31/01/2021 | - | 100% |
3 | Third Mile Stone | A- Activity completion of Civil Work: (a) RCC slab upto floor level 8 (b) Brick/Block work upto floor level 6 (c) Internal finishing works upto floor level 4 (d) Water proofing works, C.I, G.I., S.S internal plumbing work, wall tiling etcwork upto floor level 4 (e) Finalization & approval of Sample Flat including all fittings at groundfloor complete in all respect including electrical works B- Activity completion of E&M work: (a) Slab conduiting upto level 8 (b) Wall conduiting, fixing o | 01/02/2021 | 30/04/2021 | - | 100% |
4 | Fourth Mile Stone | A- Activity completion of Civil Work: (a) RCC slab upto floor level 12 (terrace level) (b) Brick work upto floor level9 (c) Internal finishing works upto floor level 7 (d) Water proofing works, C.I, G.I., S.S internal plumbing work, wall tiling etcwork upto floor level 6 B- Activity completion of E&M work: (a) Slab conduiting upto floor level 12 (b) Wall conduiting, fixing of switch, socket boxes and DBs upto floor level 7 (c) Making of holes in toilets, rooms, kitchen etc., firef | 01/05/2021 | 31/07/2021 | - | 100% |
5 | Fifth Mile Stone | A- Activity completion of Civil Work: (a) Over Head water tanks, mumty, Brick coba complete (b) Completion of AAC/Brick works & all plastering works (c) Complete toilet work including all internal plumbing works,wall tiling works etc. (d) Completion of all flooring works etc. complete in all respect. B- Activity completion of E&M work: (a) Wall conduiting, fixing of switch, socket boxes and DBs of all floors (b) Making of holes in toilets, rooms, kitchen etc.,fire fightingand exhaust etc. up | 01/08/2021 | 31/10/2021 | - | 40% |
6 | Sixth Mile Stone | A- Activity completion of Civil Work: (i) Completion of internal & external painting& false ceiling works (ii) Completion of external plumbing, sewerage work, drainage, road work, pathways, area developmentandboundary & gate work, etc. complete. B- Activity completion of E&M work: (a) Installation of fan and fittings in all buildings complete. (b) Completion & testing of fire fighting work in all building including pump room & yard hydrant work and submission for inspection by CFO. (c) Com | 01/11/2021 | 31/01/2022 | - | 1% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Released Budget(In Lac) | Expenditure till date (In Lac) C | Total Revised Budget (In Lac)B | Balance Fund (In Lac) (A+B-C) |
5000 Lac. | 5000 Lac. | 3500 Lac. | 0 Lac. | 1500 Lac. |
BUDGET RECEIVED IN INSTALLMENT | ||||
---|---|---|---|---|
Sr.No. | Installment Amount (In Lac) | Amount Recived Date | Utilization certificate(UC) | |
1 | 0.04444 | 18/Oct/2023 |